Fehmarnbelt Tunnel start looms on the horizon - 2020

Work on the €7 billion immersed tunnel under the Fehmarnbelt could begin in 2020, according to the Danish state planning and operating company Femern. A construction start has been delayed on the 18km tunnel that will run between Germany and Denmark because of environmental and consultation issues in Germany. But Claus Baunkjaer, chief executive of Femern, said he is confident that Germany will give approval next year with another two years of preparations. Baunkjaer noted that Denmark is all set to p
October 20, 2017 Read time: 3 mins
Fehmarnbelt Tunnel: a start is in sight, according to Claus Baunkjaer, head of Femern
Work on the €7 billion immersed tunnel under the Fehmarnbelt could begin in 2020, according to the Danish state planning and operating company 4782 Femern.


A construction start has been delayed on the 18km tunnel that will run between Germany and Denmark because of environmental and consultation issues in Germany. But Claus Baunkjaer, chief executive of Femern, said he is confident that Germany will give approval next year with another two years of preparations.

Baunkjaer noted that Denmark is all set to proceed with its part of the work. The finances have been secured and the construction firm has been chosen.

The Fehmarn Belt is a strait between the German island of Fehmarn and the Danish island of Lolland. Currently, a ferry connects the two islands. Final planning approval is expected in 2018 with project completion by 2028. But the approval process has been bogged down over environmental issues being considered by the German state of Schleswig-Holstein in which the southern end of 18km immersed tunnel will surface.

On top of the €7 billion construction cost for the tunnel, financing for another €1 billion is in place should it be needed for unexpected problems and delays. Denmark is completely responsible for financing the project that will replace a ferry service.

Earlier this year, a report commissioned by German ferry operator Scandilines suggested that the Fehmarn tunnel will never be economically viable. Revenue and traffic forecasts are unrealistically high, noted the report completed by German consultancy DIW Econ. It is unlikely that the latest cost to build the massive road tunnel, around €7.4 billion, would ever be recovered.

DIW Econ’s 13-page report is based around mathematical calculations of a price war between the ferry and tunnel operators. Tunnel operator Fixed Link has said it will charge around €65 per car and €267 for a truck. The report suggests that the ferry operator will undercut the tunnel operator by half, and take 37% of the car market and retain at least 80% of the truck market.

“This will secure the ferry a decent profit, so that the ferry will stay in the market,” notes the authors. “The report finds that in the baseline scenario the tunnel incurs a loss of at least €3 billion over the 50 years [concession] due to the large market shares captured by the ferry.”

The report says that Fixed Link will make a profit only if the ferry services ceases operations. However, there are variables, acknowledge the authors, and the calculations and results could change with time.

Femern dismissed the claims. The project's financial situation is secure according to financial analysis of the project by international auditors on behalf of the Danish Ministry of Transport. Femern also said that the project will be paid off over 36 years, as noted in the original plans.

For more information on companies in this article

Related Content

  • Tunnel or bridge link for Sri Lanka-India?
    June 24, 2015
    Plans are being considered for either a tunnel or bridge to connect Sri Lanka and India. The preferred route would be from Dhanushkodi in India to Talaimannar on the Sri Lankan island of Mannar. Building this 23km link could cost around US$3.62 billion according to estimates. Spanning the Pak Strait with a bridge might leave such a structure vulnerable to tsunami as well as typhoons however. It is worth noting that Sri Lanka’s south western coast was devastated some years ago by a tsunami precipitated by an
  • Euromarket stable until 2020, predicts Euroconstruct
    December 13, 2018
    Analysts predict strong growth in road building up to 2020 as public finances improve. Graham Anderson reports from Helsinki European civil engineering markets – including road building and maintenance - are predicted to grow strongly between now and 2020 thanks to the increasing strength of EU members states’ national economies. The increasingly optimistic forecasts are contained in the latest construction industry research from construction market analyst Euroconstruct, based in the Finnish capital Hel
  • Volvo CE’s Carl Slotte explains the division’s current line-up
    October 11, 2017
    Next year Volvo CE will be testing electric, hybrid and autonomous vehicles in a quarry. Carl Slotte, head of sales for EMEA, says no company by itself will win market share. David Arminas reports from Germany The driver of the charter bus stood outside the hotel in Trier, Germany, and waved at a passing local city bus. “I know the driver,” he told one of the assembled journalists waiting for the group’s ride to the nearby Volvo CE plant. “He is retired but they brought him back because young people th
  • Possible delays for Gordie Howe Bridge
    November 15, 2022
    The tolled six-lane cable-stayed bridge over the Detroit River will connect the city of Windsor in the Canadian province of Ontario with Detroit in the neighbouring US state of Michigan.