Fehmarnbelt Tunnel start looms on the horizon - 2020

Work on the €7 billion immersed tunnel under the Fehmarnbelt could begin in 2020, according to the Danish state planning and operating company Femern. A construction start has been delayed on the 18km tunnel that will run between Germany and Denmark because of environmental and consultation issues in Germany. But Claus Baunkjaer, chief executive of Femern, said he is confident that Germany will give approval next year with another two years of preparations. Baunkjaer noted that Denmark is all set to p
October 20, 2017 Read time: 3 mins
Fehmarnbelt Tunnel: a start is in sight, according to Claus Baunkjaer, head of Femern
Work on the €7 billion immersed tunnel under the Fehmarnbelt could begin in 2020, according to the Danish state planning and operating company 4782 Femern.


A construction start has been delayed on the 18km tunnel that will run between Germany and Denmark because of environmental and consultation issues in Germany. But Claus Baunkjaer, chief executive of Femern, said he is confident that Germany will give approval next year with another two years of preparations.

Baunkjaer noted that Denmark is all set to proceed with its part of the work. The finances have been secured and the construction firm has been chosen.

The Fehmarn Belt is a strait between the German island of Fehmarn and the Danish island of Lolland. Currently, a ferry connects the two islands. Final planning approval is expected in 2018 with project completion by 2028. But the approval process has been bogged down over environmental issues being considered by the German state of Schleswig-Holstein in which the southern end of 18km immersed tunnel will surface.

On top of the €7 billion construction cost for the tunnel, financing for another €1 billion is in place should it be needed for unexpected problems and delays. Denmark is completely responsible for financing the project that will replace a ferry service.

Earlier this year, a report commissioned by German ferry operator Scandilines suggested that the Fehmarn tunnel will never be economically viable. Revenue and traffic forecasts are unrealistically high, noted the report completed by German consultancy DIW Econ. It is unlikely that the latest cost to build the massive road tunnel, around €7.4 billion, would ever be recovered.

DIW Econ’s 13-page report is based around mathematical calculations of a price war between the ferry and tunnel operators. Tunnel operator Fixed Link has said it will charge around €65 per car and €267 for a truck. The report suggests that the ferry operator will undercut the tunnel operator by half, and take 37% of the car market and retain at least 80% of the truck market.

“This will secure the ferry a decent profit, so that the ferry will stay in the market,” notes the authors. “The report finds that in the baseline scenario the tunnel incurs a loss of at least €3 billion over the 50 years [concession] due to the large market shares captured by the ferry.”

The report says that Fixed Link will make a profit only if the ferry services ceases operations. However, there are variables, acknowledge the authors, and the calculations and results could change with time.

Femern dismissed the claims. The project's financial situation is secure according to financial analysis of the project by international auditors on behalf of the Danish Ministry of Transport. Femern also said that the project will be paid off over 36 years, as noted in the original plans.

For more information on companies in this article

Related Content

  • Denmark–Germany delay
    June 26, 2012
    The company handling the Fehmarnbelt tunnel project that will connect Denmark and Germany has confirmed that the project will now be delayed. Femern has revealed that construction will not start before summer 2015, a year later than originally planned. Denmark is expected to commence its environmental compatibility study in May 2013.
  • The tunnel connecting Denmark and Germany will now be delayed
    May 2, 2012
    The company handling the Fehmarnbelt tunnel project that will connect Denmark and Germany has confirmed that the project will now be delayed. Femern has now revealed that construction will not start before summer 2015, a year later than originally planned. Denmark is expected to commence its environmental compatibility study in May 2013.
  • Delays are expected for the new tunnel planned to link Denmark and Germany
    April 10, 2012
    Delays are expected for the project to build a new tunnel connecting Denmark with Germany. Femern, the firm managing the 19km Fehmarnbelt tunnel project from Denmark to Germany, has said that the current time plan is too ambitious. Femern believes that it will be 2015 rather than 2014 before work will commence. The tunnel would then open in 2012.
  • Cost of Denmark-German link
    February 20, 2012
    Discussions on a new link between Denmark and Germany continue with Denmark's Transport Ministry publishing data showing that the proposed bridge option would be more costly than a tunnel.