Skip to main content

Fehmarnbelt Tunnel start looms on the horizon - 2020

Work on the €7 billion immersed tunnel under the Fehmarnbelt could begin in 2020, according to the Danish state planning and operating company Femern. A construction start has been delayed on the 18km tunnel that will run between Germany and Denmark because of environmental and consultation issues in Germany. But Claus Baunkjaer, chief executive of Femern, said he is confident that Germany will give approval next year with another two years of preparations. Baunkjaer noted that Denmark is all set to p
October 20, 2017 Read time: 3 mins
Fehmarnbelt Tunnel: a start is in sight, according to Claus Baunkjaer, head of Femern
Work on the €7 billion immersed tunnel under the Fehmarnbelt could begin in 2020, according to the Danish state planning and operating company 4782 Femern.


A construction start has been delayed on the 18km tunnel that will run between Germany and Denmark because of environmental and consultation issues in Germany. But Claus Baunkjaer, chief executive of Femern, said he is confident that Germany will give approval next year with another two years of preparations.

Baunkjaer noted that Denmark is all set to proceed with its part of the work. The finances have been secured and the construction firm has been chosen.

The Fehmarn Belt is a strait between the German island of Fehmarn and the Danish island of Lolland. Currently, a ferry connects the two islands. Final planning approval is expected in 2018 with project completion by 2028. But the approval process has been bogged down over environmental issues being considered by the German state of Schleswig-Holstein in which the southern end of 18km immersed tunnel will surface.

On top of the €7 billion construction cost for the tunnel, financing for another €1 billion is in place should it be needed for unexpected problems and delays. Denmark is completely responsible for financing the project that will replace a ferry service.

Earlier this year, a report commissioned by German ferry operator Scandilines suggested that the Fehmarn tunnel will never be economically viable. Revenue and traffic forecasts are unrealistically high, noted the report completed by German consultancy DIW Econ. It is unlikely that the latest cost to build the massive road tunnel, around €7.4 billion, would ever be recovered.

DIW Econ’s 13-page report is based around mathematical calculations of a price war between the ferry and tunnel operators. Tunnel operator Fixed Link has said it will charge around €65 per car and €267 for a truck. The report suggests that the ferry operator will undercut the tunnel operator by half, and take 37% of the car market and retain at least 80% of the truck market.

“This will secure the ferry a decent profit, so that the ferry will stay in the market,” notes the authors. “The report finds that in the baseline scenario the tunnel incurs a loss of at least €3 billion over the 50 years [concession] due to the large market shares captured by the ferry.”

The report says that Fixed Link will make a profit only if the ferry services ceases operations. However, there are variables, acknowledge the authors, and the calculations and results could change with time.

Femern dismissed the claims. The project's financial situation is secure according to financial analysis of the project by international auditors on behalf of the Danish Ministry of Transport. Femern also said that the project will be paid off over 36 years, as noted in the original plans.

For more information on companies in this article

Related Content

  • Work to start on Fehmarn Belt link to start in autumn
    April 4, 2019
    Construction of the Fehmarn Belt Fixed Link between Denmark and Germany should start this autumn for completion in 2028, according to the Danish government. Danish company Femern, which is responsible for the construction of the link, will begin negotiations with two contractor consortiums for the first of the project’s works which will start on the Danish side. A tunnel element fabrication yard and a works harbour must be built in Rødbyhavn, as well as a tunnel portal on Lolland. An autumn start wou
  • Electrical tender launched for Fehmarn tunnel
    February 10, 2021
    The winner must set up a renewable energy centre for its work.
  • Denmark set to appoint preferred bidder for Fehmarnbelt link
    March 14, 2016
    The Danish political parties behind the Fehmarnbelt link have mandated Femern A/S to appoint preferred bidders for the main tunnel work in order to enter into conditional contracts no later than mid-May. Femern A/S is the Danish government-owned company managing the Fehmarn Belt immersed tunnel project between Denmark and Germany. The project was approved by the Danish parliament in April last year. It is supposed to be built, owned - apart from the German land works - and operated by Femern A/S, a su
  • Fehmarn tunnel cleared for construction
    October 18, 2021
    The 17.6km Fehmarnbelt tunnel will be between Germany and Denmark.