Fehmarnbelt hearings to start

The Danish-German project has come under financial and environmental criticism.
By David Arminas September 24, 2020 Read time: 2 mins
A four-lane motorway and double-track electric railway tunnel will run under the Baltic Sea strait

A German court will soon open proceedings in seven lawsuits against the planned rail and road link between the German island of Fehmarn and Denmark.

A four-lane motorway and double-track electric railway tunnel will run under the Fehmahrnbelt strait and the Danish government is shouldering the estimated €7.4 billion (US$8.54 billion) construction cost. The cases have been brought by environmental organisations, a farmer, communal authorities and two ferry operators whose services the project likely make redundant.

The ambitious project has run into repeated financial and environmental criticism since it was agreed several years ago by the two national governments to get the project underway. It will allow trains to cross the strait in just seven minutes and take cars ten minutes respectively. Currently, a ferry takes about an hour to make the crossing.

The Fehmarnbelt link will be built as an immersed tunnel. Hollow 73,000-tonne concrete elements, cast on land, will be barged out to sea and lowered into place along a 60m-wide, 16m-deep trench in the seabed.

In July, German and Danish media reported that around 30 supporters and activists of the Beltretter protest group held a gathering standing in the Baltic Sea at the Grüner Brink nature reserve near the Puttgarden ferry pier. They held a banner that read ‘Protect the Baltic Sea. Stop tunneling’ and voiced concern over possible damage to the environment and tourism in the Bay of Lübeck.

A Rambøll-Arup-TEC consultancy joint venture is engaged in a client consultancy services contract with Femern. The joint venture has also worked on other landmark infrastructure projects, including the Øresund Tunnel in Denmark, the City Tunnel in Malmö, Sweden, the Medway Tunnel in England, as well as underground rail systems in Amsterdam and Copenhagen.

COWI is carrying out the detailed design of the tunnel (north tunnel section, south tunnel section, and ramps & portals). Meanwhile, SWECO is handling the design for the dredging and reclamation work.

 

For more information on companies in this article

Related Content

  • The tunnel connecting Denmark and Germany will now be delayed
    May 2, 2012
    The company handling the Fehmarnbelt tunnel project that will connect Denmark and Germany has confirmed that the project will now be delayed. Femern has now revealed that construction will not start before summer 2015, a year later than originally planned. Denmark is expected to commence its environmental compatibility study in May 2013.
  • Developments in cycle way monitoring
    February 13, 2012
    A new cycle way monitoring system developed by consultant Cowi and laser electronics company Dynatest in Denmark adds a new dimension to monitoring local road networks. It is developed from standard road condition measurements but is specially tailored for the bicycle path and the particular ride conditions needed for cyclists. The need is growing as the bicycle lane becomes increasingly important around the world. In London a number of special bicycle "super highways" have been introduced, marking off bicy
  • Work underway for Brazil’s Santos-Guarujá Tunnel
    January 12, 2024
    Work is underway for Brazil’s Santos-Guarujá Port Tunnel project.
  • Shortlist announced for International Tunnelling and Underground Space Association (ITA) Awards
    September 23, 2015
    More than 30 nominated companies and individual will be running for the International Tunnelling and Underground Space Association’s (ITA) Awards. The awards, to be held in Hagerbach, Switzerland on November 19, consist of nine categories, from ‘Major Project of the Year’ to the ‘Innovation of the year’. Nominee selection was difficult because of the high number of quality applicants – 110 – and impressive projects – 105 – that the judges had to examine. Finally, three to eight nominees were selected