Fehmarn Belt Fixed Link could open by 2025 at earliest

The ambitious Fehmarn Belt Fixed Link, connecting Denmark and Germany, will open in 2025 at the earliest, according to the Danish finance ministry. Femern A/S, the Danish government-owned company managing the project, confirmed the note from the government. It also said the ministry still has financial concerns over the deal to build an immersed tunnel connecting the towns of Rødby in Denmark’s southern Zealand with Puttgarden in northern Germany. Of particular is the time for a construction company t
November 27, 2015 Read time: 3 mins
The ambitious Fehmarn Belt Fixed Link, connecting Denmark and Germany, will open in 2025 at the earliest, according to the Danish finance ministry.

4782 Femern A/S, the Danish government-owned company managing the project, confirmed the note from the government. It also said the ministry still has financial concerns over the deal to build an immersed tunnel connecting the towns of Rødby in Denmark’s southern Zealand with Puttgarden in northern Germany.

Of particular is the time for a construction company to receive full payback for the project because of declining traffic volume forecasts.

Financing includes European Union subsidies amounting to nearly €590 million during 2016-2019, but with delays to start of construction subsidies may be cut back.

World Highways reported in October that a study by Danish consultant Hans Schjær-Jacobsen had shown that payback period for the proposed 17km tunnel would be close to 50 years. This is a decade longer than estimated by the developers of the project, the study noted.

The Fehmarn Belt Fixed Link will connect the German island of Fehmarn with the Danish island of Lolland. The tunnel, incorporating two railway tunnels, two motorway tunnels and an emergency tunnel, will cross the Fehmarn Belt, or Fehmarn Strait, in the Baltic Sea.

According to the study, driver fees alone are unlikely to be sufficient for the financing of the link. Danish taxpayers will likely have to contribute to the project. More research is needed to pinpoint the finer details of the project whose estimated cost has been rising over the past year.

The Fehmarn Belt immersed tunnel project was approved by the Danish parliament in April this year. It is supposed to be built, owned - apart from the German land works - and operated by a Danish state agency called Femern, a subsidiary of Sund & Bælt Holding, and financed by loans guaranteed by the Danish government.

World Highways also reported in February that the Danish government was talking to contractors over the latest rise, a jump of €1.2 billion, in cost estimates for entire project. Contractors estimated an extra €295.5 million will be needed.

This is in addition to a statement in November 2014 by the contracting company Femern saying that costs had risen nearly by €900 million.

For more information on companies in this article

Related Content

  • BAM wins motorway deals in The Hague and Munich
    December 7, 2015
    The Dutch city of The Hague has awarded a BAM joint venture with a €300 million design, construction and maintenance contract for a 4km city road. The new connecting road will run between the motorway at the Ypenburg interchange, A4 and A13, and The Hague’s Central Zone of Binckhorst-Centrum-Scheveningen. Construction will start in mid-2016 and the road is expected to be open by early 2020. The Rotterdamsebaan will make The Hague and its immediate region better accessible by connecting the A4 /A13
  • Legal battle for Croatia’s Peljeski Bridge contract continues
    April 19, 2018
    Only days after Croatia rejected initial complaints, contractors Astaldi, Ictas and Strabag said that they will submit new complaints over the Peljeski bridge winning bid. Croatian media report that Turkey's Ictas, Italy's Astaldi and the Austrian company Strabag are planning to submit a new complaint to the Croatian High Court against a decision by the state procurement authority DKOM to reject their previous complaints. At issue is the awarding of the Peljeski bridge and access roads project to the
  • Property issues holding back start of work on Gordie Howe Bridge
    July 19, 2016
    Delays in buying properties in Detroit, Michigan, could hold up construction of the proposed 3.2km Gordie Howe International Bridge that will link the US city to Windsor in Canada. A report by the Detroit Free press said that around 30 of the estimated 900 parcels of land in the city’s Delray district could pose potential problems if owners resist selling the sites to the bridge’s developers. The newspaper noted that Dwight Duncan, interim chair of the Windsor-Detroit Bridge Authority - the Canadian e
  • The world’s longest suspension bridge
    June 24, 2024
    The world’s longest suspension bridge is the 1915 Çanakkale Bridge in Turkey. This engineering marvel links Gelibolu with Lapseki, forming a key section of the 101km highway linking Malkara with Çanakkale. *Article produced in partnership with the General Directorate of Highways (KGM), Ministry of Transport and Infrastructure, Republic of Türkiye.