Croatia’s Peljesac Bridge progressing

China Road and Bridge Corporation is working through the pandemic period.
By David Arminas June 11, 2020 Read time: 2 mins
CRBC started construction in the Bay of Mali Ston in January 2019 (photo courtesy of Hrvatske ceste/Croatian Roads Authority)

The first pier for Croatia’s Peljesac Bridge is rising above the waterline of the Bay of Mali Ston, according to reports by Croatian media.

The bridge is being built by China Road and Bridge Corporation (CRBC), part of the Chinese state-owned China Communications Construction Company.  CCCC was formed through the merger of CRBC and China Harbour Engineering in 2005.

CRBC started construction in the bay in January 2019. The contract, a US$340m project, is the first time that a Chinese company had won a bid for a project funded by the European Union. It is also part of China’s Belt and Road Initiative to fund and construct major infrastructure between China through Asia to the Middle East, Africa and Europe.

Strabag, which bid for the project, was chosen for only the access roads to the bridge and cited unfair competition by a state funded company. The major issue was CRBC’s bid being around 20% cheaper than Strabag’s bid. A legal challenge to have the contract overturned was unsuccessful.

Croatian media recently reported that prime minister Andrej Plenkovic, the minister of transport and other cabinet members visited the construction site. Plenkovic praised the workers and companies for using safe working methods during the ongoing pandemic.

Around 80% of the cost will be co-financed by the European Commission’s body for large infrastructure projects, JASPERS - Joint Assistance to Support Projects in European Regions.

According to construction plans accepted in 2007, the project is for a 21m-wide cable-stayed bridge carrying four lanes across the entrance to Mali Ston Bay. The main span would be 568m and likely be the second largest in Europe. The two main pylons would reach 170m above sea level.

The project also calls for access roads at both sides of the bridge. Work would include two tunnels on Pelješac island - one nearly 2.2km long and the other at 450m - as well as two smaller bridges on Pelješac, one 500m long and the other only 50m.

Once completed, this bridge would physically link Peljesac to mainland Croatia, which is now interrupted by a strip of land belonging to Bosnia and Herzegovina.

Start of construction had been continuously delayed until shipping rights and boundaries were better defined between the two countries.

There had been concerns by Bosnia about possible obstruction of cargo ships bound into the bay for the Bosnian city of Neum. The Bosnian government is planning to upgrade the infrastructure of Neum, the only Adriatic Sea access for Bosnia along its brief 20km of coastline.

For more information on companies in this article

Related Content

  • The doors open on a record-breaking bauma China 2018
    November 22, 2018
    You can tell a lot from numbers – and this year’s bauma China exhibition is set to be a record-breaker! The exhibitor numbers represent an impressive 11% increase on the 2,958 exhibitors from 41 countries that presented their products and innovations to around 170,000 visitors at the 2016 event.
  • Signify to light up Massey Tunnel
    January 15, 2021
    The LED replacements in the Vancouver area tunnel are Lumec TunnelView, made by Signify.
  • PERI helping to build world’s longest underwater tunnel
    April 4, 2013
    In China, PERI is playing a crucial role in the construction of the world’s longest underwater tunnel The 6km tunnel is part of a new 35km long road connection across the Pearl River bay in southern China, aiming to allow Hong Kong to grow both physically and economically with Macau and also Zhuhai on mainland China. In a huge field factory near the underwater tunnel site, two production lines are being used to produce a total of 33 tunnel elements. Each of the reinforced concrete tubes for the standard sec
  • A decade for completing the 105km Cork-Limerick M20
    December 10, 2018
    It could be a decade before Ireland’s 105km Cork-Limerick M20 motorway is finished, the government has warned. Road safety groups and businesses have been pushing for the €900m M20 motorway because of issues over fatalities on the existing rural route. Simon Coveney, Ireland’s deputy prime minister, said the government was committed to the route – the largest motorway project to be undertaken in the next 25 years, and money has been earmarked for it. According to Irish media, Coveney also noted tha