Croatia’s Peljesac Bridge progressing

China Road and Bridge Corporation is working through the pandemic period.
By David Arminas June 11, 2020 Read time: 2 mins
CRBC started construction in the Bay of Mali Ston in January 2019 (photo courtesy of Hrvatske ceste/Croatian Roads Authority)

The first pier for Croatia’s Peljesac Bridge is rising above the waterline of the Bay of Mali Ston, according to reports by Croatian media.

The bridge is being built by China Road and Bridge Corporation (CRBC), part of the Chinese state-owned China Communications Construction Company.  CCCC was formed through the merger of CRBC and China Harbour Engineering in 2005.

CRBC started construction in the bay in January 2019. The contract, a US$340m project, is the first time that a Chinese company had won a bid for a project funded by the European Union. It is also part of China’s Belt and Road Initiative to fund and construct major infrastructure between China through Asia to the Middle East, Africa and Europe.

Strabag, which bid for the project, was chosen for only the access roads to the bridge and cited unfair competition by a state funded company. The major issue was CRBC’s bid being around 20% cheaper than Strabag’s bid. A legal challenge to have the contract overturned was unsuccessful.

Croatian media recently reported that prime minister Andrej Plenkovic, the minister of transport and other cabinet members visited the construction site. Plenkovic praised the workers and companies for using safe working methods during the ongoing pandemic.

Around 80% of the cost will be co-financed by the European Commission’s body for large infrastructure projects, JASPERS - Joint Assistance to Support Projects in European Regions.

According to construction plans accepted in 2007, the project is for a 21m-wide cable-stayed bridge carrying four lanes across the entrance to Mali Ston Bay. The main span would be 568m and likely be the second largest in Europe. The two main pylons would reach 170m above sea level.

The project also calls for access roads at both sides of the bridge. Work would include two tunnels on Pelješac island - one nearly 2.2km long and the other at 450m - as well as two smaller bridges on Pelješac, one 500m long and the other only 50m.

Once completed, this bridge would physically link Peljesac to mainland Croatia, which is now interrupted by a strip of land belonging to Bosnia and Herzegovina.

Start of construction had been continuously delayed until shipping rights and boundaries were better defined between the two countries.

There had been concerns by Bosnia about possible obstruction of cargo ships bound into the bay for the Bosnian city of Neum. The Bosnian government is planning to upgrade the infrastructure of Neum, the only Adriatic Sea access for Bosnia along its brief 20km of coastline.

For more information on companies in this article

Related Content

  • Kewatkhali Bridge construction to start
    October 11, 2023
    The project in Bangladesh for the steel arch bridge includes a 6.2km four-lane approach road.
  • Koh Samui-Surat Thani bridge still on
    April 14, 2025
    Surachet Laopoolsuk, head of the Expressway Authority, Exat, reportedly said that the bridge could be open by 2034.
  • Indonesia’s Trans-Sumatra highway inches ahead
    March 11, 2015
    Indonesia will form a consortium of state enterprises to build all the 2,700km of the Trans-Sumatra toll highway, from Lampung to Aceh on the island of Sumatra. The finance department is also setting up special infrastructure banks to provide flexible loans for the state departments to fund the project, Indonesian media reported. Indonesia recently changed the law that had the state infrastructure company PT Hutama Karya as the only organisation allowed to build major projects. Other state enterprises can n
  • New highway connections planned for Serbia
    September 6, 2012
    The authorities in Serbia are pushing ahead with plans for the Corridor 10 and Corridor 11 highways. Serbia's national state owned highway company, Koridori Srbije, has awarded the contract for advisory services for the €1.9 billion Corridor 10 project to French company Egis International. Under the terms of the deal Egis will provide support for construction of 83.4km of the E-80 highway between the City of Nis and the Bulgarian border at Dimitrovgrad.