Croatia’s Peljesac Bridge progressing

China Road and Bridge Corporation is working through the pandemic period.
By David Arminas June 11, 2020 Read time: 2 mins
CRBC started construction in the Bay of Mali Ston in January 2019 (photo courtesy of Hrvatske ceste/Croatian Roads Authority)

The first pier for Croatia’s Peljesac Bridge is rising above the waterline of the Bay of Mali Ston, according to reports by Croatian media.

The bridge is being built by China Road and Bridge Corporation (CRBC), part of the Chinese state-owned China Communications Construction Company.  CCCC was formed through the merger of CRBC and China Harbour Engineering in 2005.

CRBC started construction in the bay in January 2019. The contract, a US$340m project, is the first time that a Chinese company had won a bid for a project funded by the European Union. It is also part of China’s Belt and Road Initiative to fund and construct major infrastructure between China through Asia to the Middle East, Africa and Europe.

Strabag, which bid for the project, was chosen for only the access roads to the bridge and cited unfair competition by a state funded company. The major issue was CRBC’s bid being around 20% cheaper than Strabag’s bid. A legal challenge to have the contract overturned was unsuccessful.

Croatian media recently reported that prime minister Andrej Plenkovic, the minister of transport and other cabinet members visited the construction site. Plenkovic praised the workers and companies for using safe working methods during the ongoing pandemic.

Around 80% of the cost will be co-financed by the European Commission’s body for large infrastructure projects, JASPERS - Joint Assistance to Support Projects in European Regions.

According to construction plans accepted in 2007, the project is for a 21m-wide cable-stayed bridge carrying four lanes across the entrance to Mali Ston Bay. The main span would be 568m and likely be the second largest in Europe. The two main pylons would reach 170m above sea level.

The project also calls for access roads at both sides of the bridge. Work would include two tunnels on Pelješac island - one nearly 2.2km long and the other at 450m - as well as two smaller bridges on Pelješac, one 500m long and the other only 50m.

Once completed, this bridge would physically link Peljesac to mainland Croatia, which is now interrupted by a strip of land belonging to Bosnia and Herzegovina.

Start of construction had been continuously delayed until shipping rights and boundaries were better defined between the two countries.

There had been concerns by Bosnia about possible obstruction of cargo ships bound into the bay for the Bosnian city of Neum. The Bosnian government is planning to upgrade the infrastructure of Neum, the only Adriatic Sea access for Bosnia along its brief 20km of coastline.

For more information on companies in this article

Related Content

  • Legal battle for Croatia’s Peljeski Bridge contract continues
    April 19, 2018
    Only days after Croatia rejected initial complaints, contractors Astaldi, Ictas and Strabag said that they will submit new complaints over the Peljeski bridge winning bid. Croatian media report that Turkey's Ictas, Italy's Astaldi and the Austrian company Strabag are planning to submit a new complaint to the Croatian High Court against a decision by the state procurement authority DKOM to reject their previous complaints. At issue is the awarding of the Peljeski bridge and access roads project to the
  • Seven bids submitted for Croatia’s Peljeski bridge access roads
    June 18, 2018
    Croatia’s construction company Integral Inzinjering has submitted the lowest bid of €43 million for construction of access roads for the Peljeski bridge project. Croatian daily newspaper Vecernji List reported that seven bidsd were submitted for the 12.4km project. Highest bid of €88 million has come from China Road and Bridge Corporation, which has the contract to build the bridge. Austria's Strabag offered €65 million. Other bidders were France's Colas, Croatia's GP Krk in cooperation with the Bosni
  • CT Ictas and Astaldi submit complaint over Peljeski Bridge award
    February 14, 2018
    Croatian media are reporting a dispute between two consortia and that of the China Road and Bridges over the Peljeski bridge project. Croatia’s national roads company Hrvatske Ceste chose China Road and Bridges but the decision is being challenged by a consortium led by the Italian firm Astaldi and one by Turkish CT Ictas. The two consortia submitted their complaints to the Croatian State Commission for Control of Public Ordering Processes in January only days after similar action by another consortia led
  • Croatia rejects complaints over Peljeski Bridge tender
    April 6, 2018
    Croatia’s public procurement body has rejected complaints by all three international consortia over a winning low tender for the Peljeski bridge. Bids for construction of the four-lane 2.4km bridge were submitted in the middle of last year. The bridge will connect Croatian territory by traversing the Adriatic Sea’s Mali Ston Bay. Vehicles must currently head from Croatia into Bosnia to re-enter a peninsula that is Croatian territory. Croatia’s State Commission for Control of Public Ordering Processes