Costa Rica road projects moving forward - slowly

Costa Rica is moving ahead with a series of major road projects, but progress is proving slower than anticipated or desired. The Costa Rica Government is struggling to achieve satisfactory progress with its overall road improvement programme. So far the key focus has been on maintaining existing links rather than building and improving road connections. The country’s National Laboratory for Structural Material and Models (Lanamme) has produced a report revealing that 85% of the national roads are in accepta
July 18, 2017 Read time: 3 mins
Costa Rica is moving ahead with a series of major road projects, but progress is proving slower than anticipated or desired. The Costa Rica Government is struggling to achieve satisfactory progress with its overall road improvement programme. So far the key focus has been on maintaining existing links rather than building and improving road connections. The country’s National Laboratory for Structural Material and Models (Lanamme) has produced a report revealing that 85% of the national roads are in acceptable condition. However the report also reveals that the Costa Rica Government is focussing on repairing roads instead of upgrading them significantly. Although Costa Rica has managed to increase the percentage of roads in good condition from 38% in 2015 to 48% at present, the country has many roads in need of major repairs according to the report. And some roads have merely been patched rather than having the major upgrades required according to the report.


Meanwhile uncertainty surrounds the start date for improvement works for a key stretch of road. The project to widen and upgrade Route 32 is being carried out by Chinese contractor China Harbour Engineering Company (CHEC). The timeline originally called for the construction work to commence in September 2017 but this may be put back to mid-2018. The contractor says that the land expropriation process has still to be completed while various licences have also to be procured, plans for moving utilities have to be completed and some stretches of the route may require archeological investigations. CHEC plans to deliver the project's final design to the national road authority, Consejo Nacional de Vialidad (2538 Conavi), on 15th August 2017. The project is being financed with a loan worth US$320 million from the Chinese Eximbank. A further $100 million for the work is being provided by the Costa Rica Government.

Problems also surround plans to build a 30km stretch of road linking Sifon, in San Ramon, with La Abundancia, in San Carlos. Costa Rica’s Treasury Inspector's Office (CGR) has not given approval for a $24.6 million increase in the value of a contract with Sanchez Carvajal. In addition CGR has also turned down a request for an extension to the time required for the work. CGR says that there are no assurances that the increased budget and time for the work will ensure its completion. Meanwhile Conavi has previously voiced its concern over the work, requesting a change to the contract and assurances that sufficient financing would be in place. The work was previously expected to cost $164 million but CGR now believes that the work will cost $213 million. The project has had a troubled past as work was originally started by a Taiwanese contractor in the third quarter of 2005. But the works hit problems and activity ceased in mid-2008, with Sanchez Carvajal then taking over the contract at a later date. The stretch from Sifon to La Abundancia forms the central section of a road new connection with San Carlos but the work has been afflicted by a series of delays arising from technical, financial and environmental challenges.

For more information on companies in this article

Related Content

  • Stonehenge tunnel going ahead?
    September 12, 2017
    The preferred route has been announced for a new road and tunnel link on the A303 route in the UK that will bypass the famous Stonehenge stone circle. The project now finally looks as if it might go ahead after years of debate, although several hurdles have yet to be passed. The work calls for the construction of a new 13km dual carriageway link and includes a 2.6km stretch of tunnel. The new route will be located further away from Stonehenge and the tunnel is being built
  • Egypt’s road programme is now restarting
    February 20, 2014
    Egypt is developing its road network – local reporting and images by Egypt correspondent Mohammed Elsayed Tantawy. Egypt is now gearing up its road construction activity, with a view to reducing congestion and improving traffic flow. The country’s main highway connecting capital Cairo with the port city of Alexandria has already seen a major widening programme, but other important routes are also now being upgraded and improved. The road development programme started in earnest some years ago but was delaye
  • Columbia kick-starts Antioquia project with Toyo tunnel financing
    January 6, 2015
    Columbia’s National Infrastructure Agency (ANI) will help finance construction of the Toyo tunnel in Antioquia. The tunnel, nearly 10km-long and costing almost US$760, will be part of a new 39km road between Santa Fe de Antioquia and Canasgordas. The central government will contribute $216 million towards the project, the regional government of Antioquia will contribute $337 million and the Medellin government will pitch in with $212 million.
  • Loans for planned Paraguayan projects
    September 22, 2014
    Financing has been found for road repairs and rebuilding in Paraguay. A series of planned projects will see roads and bridge being refurbished and rebuilt. The Latin American Development Bank (CAF) will provide loans worth US$272 million for road and bridge repairs. A $50 million loan will be used to pay for work in the country’s Oriental region. In all 110 bridges will be built across Paraguay. A loan will also pay for improvements to National Route 9 connecting Mariscal Estigarribia and La Patria and La P