Skip to main content

Costa Rica road projects moving forward - slowly

Costa Rica is moving ahead with a series of major road projects, but progress is proving slower than anticipated or desired. The Costa Rica Government is struggling to achieve satisfactory progress with its overall road improvement programme. So far the key focus has been on maintaining existing links rather than building and improving road connections. The country’s National Laboratory for Structural Material and Models (Lanamme) has produced a report revealing that 85% of the national roads are in accepta
July 18, 2017 Read time: 3 mins
Costa Rica is moving ahead with a series of major road projects, but progress is proving slower than anticipated or desired. The Costa Rica Government is struggling to achieve satisfactory progress with its overall road improvement programme. So far the key focus has been on maintaining existing links rather than building and improving road connections. The country’s National Laboratory for Structural Material and Models (Lanamme) has produced a report revealing that 85% of the national roads are in acceptable condition. However the report also reveals that the Costa Rica Government is focussing on repairing roads instead of upgrading them significantly. Although Costa Rica has managed to increase the percentage of roads in good condition from 38% in 2015 to 48% at present, the country has many roads in need of major repairs according to the report. And some roads have merely been patched rather than having the major upgrades required according to the report.


Meanwhile uncertainty surrounds the start date for improvement works for a key stretch of road. The project to widen and upgrade Route 32 is being carried out by Chinese contractor China Harbour Engineering Company (CHEC). The timeline originally called for the construction work to commence in September 2017 but this may be put back to mid-2018. The contractor says that the land expropriation process has still to be completed while various licences have also to be procured, plans for moving utilities have to be completed and some stretches of the route may require archeological investigations. CHEC plans to deliver the project's final design to the national road authority, Consejo Nacional de Vialidad (2538 Conavi), on 15th August 2017. The project is being financed with a loan worth US$320 million from the Chinese Eximbank. A further $100 million for the work is being provided by the Costa Rica Government.

Problems also surround plans to build a 30km stretch of road linking Sifon, in San Ramon, with La Abundancia, in San Carlos. Costa Rica’s Treasury Inspector's Office (CGR) has not given approval for a $24.6 million increase in the value of a contract with Sanchez Carvajal. In addition CGR has also turned down a request for an extension to the time required for the work. CGR says that there are no assurances that the increased budget and time for the work will ensure its completion. Meanwhile Conavi has previously voiced its concern over the work, requesting a change to the contract and assurances that sufficient financing would be in place. The work was previously expected to cost $164 million but CGR now believes that the work will cost $213 million. The project has had a troubled past as work was originally started by a Taiwanese contractor in the third quarter of 2005. But the works hit problems and activity ceased in mid-2008, with Sanchez Carvajal then taking over the contract at a later date. The stretch from Sifon to La Abundancia forms the central section of a road new connection with San Carlos but the work has been afflicted by a series of delays arising from technical, financial and environmental challenges.

For more information on companies in this article

Related Content

  • India’s poor road safety requires improvement
    September 13, 2016
    The Indian Government has revealed that 146,133 people died in crashes on the country’s roads during 2015. This figure is of concern as it is an increase of 4.6% over India’s road fatality rate of 139,671 for the previous year. Also of concern is the fact that over half of the people who died in crashes were aged from 15-34, revealing that there is a particularly high risk for the young on India’s roads. The data also shows that there were 501,423 reported crashes on India’s road network in 2015, an increas
  • Philippines projects proceeding as planned
    October 25, 2016
    Major expressway projects are now moving forward in the Philippines, with building due to start in the first quarter of 2017. Metro Pacific is gearing up to commence construction of the C5 Link Expressway. Meanwhile Metro Pacific Investments Corp (MPIC) has plans to commence construction of the Cavite-Laguna Expressway. The 7.6km C5 Link Expressway forms part of the Cavitex network. The US$291 million project will join the C-5 Road in Taugig to the R-1 Coastal Expressway. The $728 million Cavite-Laguna e
  • Congestion and safety concerns over Serbia’s roads
    February 23, 2012
    With traffic flows on the increase, Serbia needs to improve its road network and safety record, reports Gordon Feller. Serbia's road network needs to upgrade its road system against the backdrop of increased traffic flows. Serbia is crossed by segments of the important Trans European network (TEN). Corridor X with its branches Xb (Belgrade-Budapest) Xc (Nis-Sofia), and Xd (Nis-Presevo), represent the most important transit routes in the Republic, connecting Austria/Hungary, Slovenia/Croatia, and Bulgaria/Ma
  • Piling for a road project in tough conditions
    January 11, 2019
    Machines from Liebherr have been brought in to carry out a piling job in Colombia in tough conditions. The road network between Mosquera and Balsillas is being upgraded at a cost of some US$199.15 million. Mosquera lies on the outskirts of the capital, Bogotá, while Balsillas is to the south-west and close to the borders with Ecuador and Peru. Work started on the project to improve the 230km route in January 2016 and is expected to take until December 2021 to complete. One of the contractors involved in th