Costa Rica: Conavi gets more time and funds for road maintenance

Costa Rica’s road agency Conavi has extended the deadline and increase funds by $154 million for road repair and maintenance contracts. Contracts will be extended for the companies involved which include Constructora Meco, Grupo Orosi, Quebradores del Sur, Constructora Hernan Solis and Conansa. The Treasury Inspector's Office made the announcement, according to El Pais newspaper. Meanwhile, four banks are considering an investment in the 60km San Jose-San Ramon Road Expansion Project. They include
October 26, 2015 Read time: 2 mins
Costa Rica’s road agency 2538 Conavi has extended the deadline and increase funds by $154 million for road repair and maintenance contracts.

Contracts will be extended for the companies involved which include Constructora Meco, Grupo Orosi, Quebradores del Sur, Constructora Hernan Solis and Conansa.

The Treasury Inspector's Office made the announcement, according to El Pais newspaper.

Meanwhile, four banks are considering an investment in the 60km San Jose-San Ramon Road Expansion Project. They include the private banks of Lafise and Improsa as well as the state-owned banks Bancredito and BCR.

It is also understood that Scotiabank and BCT have withdrawn from the toll-road project for which a tender is out for the design, construction, operation and maintenance of the road for 30 years.

The government of Costa Rica is using a public works trust for the project following the failure of a previous contract granted to Brazilian construction firm OAS. The government announced in May 2013 that the $473 million contract had been “suspended”, according to a report by the Latin American business website BNamericas at the time.

Cota Rica’s national concessions agency CNC has said the project is divided into four sections, with lanes to vary between two and four. Construction includes eight bridges and 10 interchanges with eight existing interchanges to be upgraded. Five toll stations will be built.

The first 17.3km runs from the capital San José to the Juan Santamaria airport, while the second 12km stretch runs from Juan Santamaria to the Poás River. A third stretch, 28.6km, will be from Poás and the last 2.7km will run from Río Segundo to San Antonio, both within the San José area.

For more information on companies in this article

Related Content

  • Costa Rica road widening work planned
    October 1, 2019
    Road widening work is being planned on the route connecting Costa Rican capital San Jose with nearby Cartago. The work is intended to cut congestion on the route, which suffers from delays at peak periods. In all the project is expected to cost US$400 million. The work is being carried out by local contractor Meco, which is now starting with a feasibility study and drawing up preliminary plans. The route will be tolled but the Costa Rican Government says it will ensure that the tolls are kept to a low level
  • Costa Rica construction contracts
    May 22, 2020
    Costa Rica construction contracts are facing challenges.
  • Nicaragua road project funding deal
    February 1, 2018
    Nicaragua’s Ministry of Transport and Infrastructure (MTI) is setting out its road development programme for 2018. In all the plans call for the construction of 171km of roads. Work will be completed for the road from Mulukuku to Siuna, with the first 23km stretch due to open in September 2018 and the remaining 21.5km expected in December 2018. Meanwhile the road from Nueva Guinea to San Francisco should be complete by November 2018. Work started on these two routes in 2016. The project also calls for
  • Columbian company carrying out Costa Rican contract with local firm
    July 4, 2014
    Colombian contractor Mario Huertas Cotes and Costa Rican company MECO will carry out construction work on Costa Rica’s Cartagena to Barranquilla highway. The highway stretch measures some 146.7km long and the contract is worth US428.9 million. The two construction companies have come together to carry out the contract jointly and won the deal with a low priced bid.