The troubled tunnel construction project in Colombia to build the La Linea link has faced yet a further setback in its long tale of woe. The tender for the completion of the final 12% of the tunnel project has not managed to attract any interest from contractors. The budget for this work is an estimated US$77 million. A new tender process is being launched, with a submission deadline of 6th June 2017 and planned winner announcement on 4th July 2017. The contractor that had been building the tunnel failed to
May 19, 2017 Read time: 2 mins
The troubled tunnel construction project in Colombia to build the La Linea link has faced yet a further setback in its long tale of woe. The tender for the completion of the final 12% of the tunnel project has not managed to attract any interest from contractors. The budget for this work is an estimated US$77 million. A new tender process is being launched, with a submission deadline of 6th June 2017 and planned winner announcement on 4th July 2017. The contractor that had been building the tunnel failed to meet the necessary completion deadline and was involved in a dispute with Colombia's National Road Institute (2812 Invias), resulting in the firm losing the contract. However the project has been delayed previously on many occasions and for many reasons, including having the wrong kind of insurance cover for the work and due to more challenging than anticipated geological conditions. Construction commenced in 2004 with the breakthrough occurring in 2008, while the tunnel was originally planned for completion in mid-2016 but will not be ready for use until 2018.


When the tunnel is complete it will connect Calarcá, Quindío and Cajamarca and provide a much safer and faster transport link than the present route over a mountain pass. Travel speeds are low along the existing route, which features several sharp curves and has an unenviable record for crashes. The 8.6km tunnel will provide a new connection for the National Route 40 highway joining Bogotá with Cali as well as the port of Buenaventura. The tunnel runs underneath the Cordillera Central range, with its western portal at an altitude of 2,420m and the eastern at 2,505m.

For more information on companies in this article

Related Content

  • Colombia’s delayed La Linea Tunnel and tertiary road development programme seeing progress
    July 6, 2017
    Progress is now being seen in Colombia with regard to key tunnel and road projects. A consortium comprising Conconcreto and CSS Constructores is to complete the 12% of work still needed to finish the La Linea Tunnel project.
  • Colombia’s La Linea Tunnel will be completed
    September 16, 2015
    Colombia's national road institute (Invias) has said that the La Linea tunnel project will open to traffic in 2017. The project has been delayed on several occasions and due to a variety of reasons, presenting a luckless and lengthy tale of woe for Colombia’s transport ministry. Early in its lifetime the project was held back by unexpected geological issues arising from more challenging ground conditions than had been initially realised. The project was also delayed by insurance problems for some of the fir
  • New tunnel link proposed for Colombia
    July 23, 2013
    Even as work continues on La Linea tunnel in Colombia, the country’s government has received a proposal for an additional tunnel link. A consortium made up of Colombian companies and Italian firms has suggested building a new tunnel to link Quindio and Tolima. Odinsa, Mincivil, Impregilo and Salini are involved in the consortium and have suggested a PPP as being a possible model under which to construct the link, which could cost in the order of US$531 million and would be 8.5km long. The economic case for
  • Colombia tunnel project conclusion plan
    December 6, 2016
    Tendering is commencing for the final portion of works to complete Colombia’s La Linea tunnel project. Around 12% of the work on the tunnel still has to be completed, with the work expected to cost US$68.5 million. The tender is being carried out by Colombia's National Road Institute (Invias). The tunnel project has been delayed for a series of reasons. Colombian contractor Constructora Carlos Collins was constructing the tunnel but did not meet the necessary deadline. As a result, Invias opted to open the