A series of major road transport projects are moving ahead in Colombia, with the country’s national infrastructure agency (ANI), handling most of the deals. In the country’s capital, Bogota, design work is now complete on the Calle 13 and Accesos Norte II road projects. The Calle 13 project will see an 11.5km section of route widened so that it features three lanes in either direction. The work will also include building new facilities for pedestrians and cyclists. This project is expected to cost US$1.15 b
May 10, 2019 Read time: 2 mins

A series of major road transport projects are moving ahead in Colombia, with the country’s national infrastructure agency (ANI), handling most of the deals. In the country’s capital, Bogota, design work is now complete on the Calle 13 and Accesos Norte II road projects. The Calle 13 project will see an 11.5km section of route widened so that it features three lanes in either direction. The work will also include building new facilities for pedestrians and cyclists. This project is expected to cost US$1.15 billion. The Accesos Norte II project meanwhile is for the rebuilding of a 10.4km stretch of road, which will feature five lanes in either direction for all vehicles as well as a dedicated bus lane. The work will cost an estimated $493 million, with funding being provided by tolling. Contracts for both the Calle 13 and Accesos Norte II road projects should be awarded by the end of 2019.

A new bridge measuring 740m is being built on the road connecting Girardot with Ibague and Cajamarca road in Tolima department. At the same time, a 6km road section is being built between Chicoral and Gualanday. Repairs and upgrade works are also being carried out on the roads connecting Bogota with Villavicencio and Bogota with Villeta. Two new interchanges are being built for the road connecting Armenia with Pereira and Manizales, with improvements also being carried out on the road linking Tibu and Convencion.

However delays to a number of projects have been caused by the termination of road contracts with Grupo Solarte. Work on the road connecting Santana with Mocoa and Neiva will now be carried out by Grupo Ethuss. This 447km road link will be handled under a concession deal. It was originally expected to cost some $956 million to carry out but now could cost as much as $1.02 billion. Work on the road connecting Popayan with Santander de Quilichao is due to commence once the contract has been agreed fully. This work is now expected to cost up to $493 million compared with the £404 million originally estimated.

Related Content

  • Three Colombian bridge projects commencing
    January 17, 2019
    In Colombia progress is being seen on three major bridge projects located in different parts of the country. Construction of the new Pumajero Bridge is well in hand and is expected to be complete before the end of 2019. The new PumajeroBbridge will be 2,247m in length and have 990m of viaduct connections and access, as well as two three-lane carriageways on each side. Once the new bridge is open to traffic, the old cable-stayed concrete link between Baranquilla and Sitionuevo will be demolished. The new
  • Key Colombia tunnel projects delayed
    September 21, 2018
    Construction work on Colombia’s two key tunnel projects is being delayed, with insufficient funding proving a major challenge. Both the Toyo Tunnel and La Linea Tunnel projects are behind schedule. In addition, the project to construct the Pumajero Bridge is also being delayed due to a lack of funds.Part of the problems is that the designs for these projects have been revised as construction work has progressed. However the additional funds to pay for the new design features added have not been fully
  • Colombia dual carriageways under construction
    October 10, 2016
    Colombia is currently working on major highway projects that will improve transport infrastructure in the country and form part of its 4G programme. The US$616.5 million Rumichaca-Pasto dual carriageway in Narino department will improve Colombia’s transport connections with neighbouring Ecuador, cutting journey times from two hours at present to just one hour. The project is being handled by a consortium, Consorcio SAC 4G and involves improving an 80km road section and building additional lanes for the 74km
  • Bidding for Uganda road connecting Kampala and Jinja
    May 22, 2018
    In Uganda bidding is now underway for the new expressway project to improve transport between capital Kampala and the industrial city of Jinja. The project for the 95km section of road is expected to cost US$1 billion to construct. The contract is being offered under the design, finance, build and operate model, with the route then being handed back to the Ugandan Government once the agreed concession period is complete. Some of the financing will be provided by the Africa Development Bank (AfDB), French De