A finance package has been secured in Colombia for the Autopista al Mar 1 highway project. A loan worth close to US$206 million is being provided by the national development bank, Financiera de Desarrollo Nacional (FDN). The highway forms part of Colombia’s 4G infrastructure development plan and the finance package will be provided in three separate tranches. The construction work is being carried out by a consortium comprising Strabag, Concay and Sacyr Concesiones. The project will upgrade the 71km
June 29, 2018 Read time: 2 mins

A finance package has been secured in Colombia for the Autopista al Mar 1 highway project. A loan worth close to US$206 million is being provided by the national development bank, Financiera de Desarrollo Nacional (FDN). The highway forms part of Colombia’s 4G infrastructure development plan and the finance package will be provided in three separate tranches.

The construction work is being carried out by a consortium comprising Strabag, Concay and Sacyr Concesiones. The project will upgrade the 71km existing route connecting Santa Fe in Antioquia and Bolombolo. The work also includes widening the 43km route between Medellin and Santa Fe, in Antioquia Department. Other key portions of the project include the construction of the 4.6km Tunel de Occidente as well as building no less than 39 bridges.

Meanwhile work to build the Toyo Tunnel (Tunel del Toyo) in Antioquia Department is now around 64% complete. The tunnel measures 9.8km long and should be ready for traffic by 2022. The link is being built bya consortium comprising FCC Construction, Cass Builders and Company, Carlos Alberto Solarte and Estyma Studies and Handling. The tunnel route runs underneath the mountains of western Antioquia, an area that is difficult to access at present due to its challenging topography. Construction of the route will improve transport to the port of Uraba, located some 80km to the north of the city of Medellin. Work is also underway on the nearby Tunel 18, a 258m tunnel section located close to Canasgordas, as well as the Puente 13 bridge and a number of access roads

However there are questions surrounding the highway widening project  for the Bogota-Girardot route. A preliminary investigation is being carried out into the construction partnership handling the $586.3 million road widening work along a 154km stretch of the highway connecting the capital Bogota with Girardot. The investigation is being carried out by the official the industry and trade watchdog (SIC), focussing on the tender process.

Related Content

  • New Argentina highway construction work
    January 11, 2019
    Construction is underway for Argentina’s new Mendoza-San Juan Highway – Mauro Nogarin reports The rehabilitation and maintenance works of more than 3,300km of routes is now underway in Argentina. This followed on after the takeover of six new road corridors under the Public-Private Partnership (PPP) model, which took place in August 2018. The rehabilitation and maintenance works are being carried out prior to the start of the main projects, which will include the construction of highways. Building the
  • A tricky road update is planned for an important rural road in Brazil
    September 27, 2013
    Brazilian consultant SOTEPA has been closely involved with infrastructure improvements in a series of projects in the southern state of Santa Catarina. One of the most important of these has been design work for the SC-477 state highway, which connects the east of the state to Brazil’s Littoral zone and the BR-101 federal highway. The SC-477 has had to be upgraded as part of it has been unsurfaced, without an asphalt surface between Itaiópolis and Doutor Pedrinho. The road provides an important link for the
  • Colombia’s delayed La Linea Tunnel and tertiary road development programme seeing progress
    July 6, 2017
    Progress is now being seen in Colombia with regard to key tunnel and road projects. A consortium comprising Conconcreto and CSS Constructores is to complete the 12% of work still needed to finish the La Linea Tunnel project.
  • Paraguay highway upgrade work planned
    August 6, 2019
    Upgrade work for Paraguay’s Route 2 is being planned. This will improve transport for the country’s capital Asunción. The road runs eastwards from the city to connect with Route 7, which connects with the Brazilian border and also lies close to the border of Argentina’s north eastern tip. Costing an estimated US$500 million, the work will be carried out by a consortium, Rutas del Este. The project is being handled under the PPP model while the consortium comprises the firms Sacyr and Ocho A. The contract w