Colombian highway projects under development

A finance package has been secured in Colombia for the Autopista al Mar 1 highway project. A loan worth close to US$206 million is being provided by the national development bank, Financiera de Desarrollo Nacional (FDN). The highway forms part of Colombia’s 4G infrastructure development plan and the finance package will be provided in three separate tranches. The construction work is being carried out by a consortium comprising Strabag, Concay and Sacyr Concesiones. The project will upgrade the 71km
June 29, 2018 Read time: 2 mins

A finance package has been secured in Colombia for the Autopista al Mar 1 highway project. A loan worth close to US$206 million is being provided by the national development bank, Financiera de Desarrollo Nacional (FDN). The highway forms part of Colombia’s 4G infrastructure development plan and the finance package will be provided in three separate tranches.

The construction work is being carried out by a consortium comprising Strabag, Concay and Sacyr Concesiones. The project will upgrade the 71km existing route connecting Santa Fe in Antioquia and Bolombolo. The work also includes widening the 43km route between Medellin and Santa Fe, in Antioquia Department. Other key portions of the project include the construction of the 4.6km Tunel de Occidente as well as building no less than 39 bridges.

Meanwhile work to build the Toyo Tunnel (Tunel del Toyo) in Antioquia Department is now around 64% complete. The tunnel measures 9.8km long and should be ready for traffic by 2022. The link is being built bya consortium comprising FCC Construction, Cass Builders and Company, Carlos Alberto Solarte and Estyma Studies and Handling. The tunnel route runs underneath the mountains of western Antioquia, an area that is difficult to access at present due to its challenging topography. Construction of the route will improve transport to the port of Uraba, located some 80km to the north of the city of Medellin. Work is also underway on the nearby Tunel 18, a 258m tunnel section located close to Canasgordas, as well as the Puente 13 bridge and a number of access roads

However there are questions surrounding the highway widening project  for the Bogota-Girardot route. A preliminary investigation is being carried out into the construction partnership handling the $586.3 million road widening work along a 154km stretch of the highway connecting the capital Bogota with Girardot. The investigation is being carried out by the official the industry and trade watchdog (SIC), focussing on the tender process.

Related Content

  • Colombia road projects delivered
    September 24, 2020
    Important road projects in Colombia have been delivered successfully.
  • Colombia road plans for capital Bogota
    December 14, 2016
    Colombia’s capital Bogota looks set to gain from key road projects, with te country’s National Infrastructure Agency (ANI) unveiling detailed plans for upcoming works. Plans are being worked on for the widening of the 53km road linking Los Andes and Cajica with the construction of an extra lane. This is a US$$156.56 million project and will be funded by private sources. The pre-feasibility study for the Autopista Norte road extension has already passed the approval stage and this project will also be funded
  • Chilean highway deals secured by Sacyr
    November 29, 2021
    Sacyr has secured major Chilean highway deals.
  • Colombia’s Tunel de Oriente delay
    August 20, 2018
    The construction of Colombia’s Tunel de Oriente project is running behind schedule. Unexpected geological problems are the reason for the delay to the project’s completion. However the builders have assured the client that the delay will not increase the cost of the project. The tunnel, located in Colombia’s Antioquia Department, was due for completion in December 2018 but will now be ready by May 2019.