Colombian highway projects under development

A finance package has been secured in Colombia for the Autopista al Mar 1 highway project. A loan worth close to US$206 million is being provided by the national development bank, Financiera de Desarrollo Nacional (FDN). The highway forms part of Colombia’s 4G infrastructure development plan and the finance package will be provided in three separate tranches. The construction work is being carried out by a consortium comprising Strabag, Concay and Sacyr Concesiones. The project will upgrade the 71km
June 29, 2018 Read time: 2 mins

A finance package has been secured in Colombia for the Autopista al Mar 1 highway project. A loan worth close to US$206 million is being provided by the national development bank, Financiera de Desarrollo Nacional (FDN). The highway forms part of Colombia’s 4G infrastructure development plan and the finance package will be provided in three separate tranches.

The construction work is being carried out by a consortium comprising Strabag, Concay and Sacyr Concesiones. The project will upgrade the 71km existing route connecting Santa Fe in Antioquia and Bolombolo. The work also includes widening the 43km route between Medellin and Santa Fe, in Antioquia Department. Other key portions of the project include the construction of the 4.6km Tunel de Occidente as well as building no less than 39 bridges.

Meanwhile work to build the Toyo Tunnel (Tunel del Toyo) in Antioquia Department is now around 64% complete. The tunnel measures 9.8km long and should be ready for traffic by 2022. The link is being built bya consortium comprising FCC Construction, Cass Builders and Company, Carlos Alberto Solarte and Estyma Studies and Handling. The tunnel route runs underneath the mountains of western Antioquia, an area that is difficult to access at present due to its challenging topography. Construction of the route will improve transport to the port of Uraba, located some 80km to the north of the city of Medellin. Work is also underway on the nearby Tunel 18, a 258m tunnel section located close to Canasgordas, as well as the Puente 13 bridge and a number of access roads

However there are questions surrounding the highway widening project  for the Bogota-Girardot route. A preliminary investigation is being carried out into the construction partnership handling the $586.3 million road widening work along a 154km stretch of the highway connecting the capital Bogota with Girardot. The investigation is being carried out by the official the industry and trade watchdog (SIC), focussing on the tender process.

Related Content

  • Work well underway on Colombian highway project
    March 13, 2018
    Work is well underway on Colombia’s US$453.43 million Conexion Pacifico II highway project. The construction work for the 96.5km highway is around 33% complete at this stage. Work is also underway on the 2.5km-long twin tube Mulatos tunnel, with around 700m having been driven so far and this portion of the project is costing nearly $127 million. The new highway will reduce journey times between Colombia’s Antioquia Department and the country’s coffee producing regions, as well as to its port of Buenaventura
  • A new highway for northern Colombia
    July 17, 2023
    The Pamplona-Cúcuta highway is playing an important role for the development of northern Colombia
  • US$443 million Medellin tunnel
    July 31, 2024
    A US$443 million road tunnel is planned for Medellin.
  • Colombia's roads to recovery
    February 8, 2012
    Colombia's Ministry of Transport is suggesting that the Avenida Longitudinal de Occidente (ALO) road project in Bogota should be carried out by Colombian energy company Empresa de Energia de Bogota (EEB).