Colombia road project - completion date announced

The completion date for Colombia’s massive Cambao-Manizales 4G road project has now been announced. The improved road link should now be read for traffic in mid-2022, according to Colombia's national infrastructure agency (ANI). The financing package for the Cambao-Manizales road project should be secured in the second half of 2019 and the construction work should commence in 2020. The project is expected to cost an initial US$363 million and the work is being carried out by Alternativas Viales, which won
July 4, 2019 Read time: 2 mins
The completion date for Colombia’s massive Cambao-Manizales 4G road project has now been announced. The improved road link should now be read for traffic in mid-2022, according to Colombia's national infrastructure agency (ANI). The financing package for the Cambao-Manizales road project should be secured in the second half of 2019 and the construction work should

commence in 2020. The project is expected to cost an initial US$363 million and the work is being carried out by Alternativas Viales, which won the concession package.

One key change to the project has been to narrow the width of the route where it passes through the Los Nevados National Park. This design change has been made to meet environmental requirements. The Cambao-Manizales road will be the 23rd of Colombia’s 4G project to get underway. By the end of 2019, work should be underway on up to 29 of Colombia’s 4G road projects.

Related Content

  • Key Colombia connection construction contract
    January 17, 2018
    Construction work on a new road link connecting Mulalo with Loboguerrero in Colombia will commence in the third quarter of 2018. The 31km link is being handled by Colombia's National Infrastructure Agency (ANI) and is expected to cost US$560.5 million. The plans are being drawn up for the project while the necessary environmental permits are being sought from Colombia’s National Environmental Licensing Agency (ANLA). The new link will be located in Colombia’s Valle del Cauca department.
  • Third phase for Colombia’s complex PPP project
    September 15, 2017
    Work is underway on the third stage of Colombia’s Bogota-Villavicencio road project. This 24km project is being carried out under the PPP model by the concession holder, Concesionaria Vial Andina (Coviandina). The project is complex and includes the construction of seven tunnels in all, which have a total length of 10.7km, as well as 21 bridges and overpasses measuring 3.8km in all. Coviandina has bored around 930m of the total tunnel length at present.
  • Consortium Via al Puerto to finish Colombia’s Buga-Buevantura road
    May 24, 2016
    Colombia’s National Infrastructure Agency (ANI) has approved Consorcio Estructura Plural Via al Puerto to build the remaining 26.5km of the Buga-Buenaventura dual carriageway. Construction costs will be just under US$358 million with another $645 million likely needed to maintain and operate the public-private partnership road for 30 years. Works include construction of two tunnels, 12 bridges, 7.5km of cycle lanes, as well as maintenance of 111km of the main road, according to a report by El Pais new
  • Washington DC’s historic bridge replacement project
    June 11, 2019
    The project to replace a historic bridge in US capital Washington DC is providing major challenges for its builders - Mike Woof writes