Colombia is establishing an action plan for its infrastructure programme, focussing on sourcing suitable financing. The country’s national road institute, Invias, is looking for US$659.5 million to carry out a series of 26 road resurfacing projects. Work on these commenced as far back as 2004 but numerous stretches remain incomplete and it will take until 2022 for the surfacing operations to be concluded. Meanwhile another new division will oversee the La Linea Tunnel and Ruta Del Sol II projects. The form
October 22, 2018 Read time: 1 min
Colombia is establishing an action plan for its infrastructure programme, focussing on sourcing suitable financing. The country’s national road institute, Invias, is looking for US$659.5 million to carry out a series of 26 road resurfacing projects. Work on these commenced as far back as 2004 but numerous stretches remain incomplete and it will take until 2022 for the surfacing operations to be concluded.


Meanwhile another new division will oversee the La Linea Tunnel and Ruta Del Sol II projects. The former is extremely complex as in addition to the main tunnel section, it also includes a further 25 minor tunnel sections and 31 stretches of elevated roads. Other key infrastructure projects being prioritised by Invias include work on the Pumarejo bridge and the road connecting La Espriella with Rio Mataje.

Related Content

  • Colombia highway plans announced
    June 4, 2020
    Key Colombian highway plans are being announced.
  • Colombia tunnel construction cost climbs
    January 25, 2018
    Work on the La Linea Tunnel project in Colombia has cost considerably more than first anticipated. The National Road Institute (Invias) says that the bill so far tops US$774 million. Extra costs of around $281.5 million have been incurred due to the need to drive a pilot tunnel as well as for three additional tunnel stretches as well as bridges along the approaches to the main tunnel. The project is now expected to be complete by the end of 2018, somewhat later than originally expected.
  • Colombia tunnel project conclusion plan
    December 6, 2016
    Tendering is commencing for the final portion of works to complete Colombia’s La Linea tunnel project. Around 12% of the work on the tunnel still has to be completed, with the work expected to cost US$68.5 million. The tender is being carried out by Colombia's National Road Institute (Invias). The tunnel project has been delayed for a series of reasons. Colombian contractor Constructora Carlos Collins was constructing the tunnel but did not meet the necessary deadline. As a result, Invias opted to open the
  • Colombia’s tunnel of woe faces further setback
    May 19, 2017
    The troubled tunnel construction project in Colombia to build the La Linea link has faced yet a further setback in its long tale of woe. The tender for the completion of the final 12% of the tunnel project has not managed to attract any interest from contractors. The budget for this work is an estimated US$77 million. A new tender process is being launched, with a submission deadline of 6th June 2017 and planned winner announcement on 4th July 2017. The contractor that had been building the tunnel failed to