Challenges mount for the Fehmarn Belt Fixed Link project

The Fehmarn Belt Fixed Link between Danish and German islands faces ongoing delays that are pushing a construction start past this year and well into 2018. A meeting in mid-December between Danish traffic minister Ole Birk Olesen and his German counterpart Reinhard Meyer for the neighbouring German state of Schleswig-Holstein, highlighted mounting opposition against the €7 billion or more project. During the meeting, Meyer stressed that the Schleswig-Holstein government remains determined to implement
December 15, 2016 Read time: 2 mins
The Fehmarn Belt Fixed Link between Danish and German islands faces ongoing delays that are pushing a construction start past this year and well into 2018.

A meeting in mid-December between Danish traffic minister Ole Birk Olesen and his German counterpart Reinhard Meyer for the neighbouring German state of Schleswig-Holstein, highlighted mounting opposition against the €7 billion or more project.

During the meeting, Meyer stressed that the Schleswig-Holstein government remains determined to implement the project even if the construction work cannot start until 2020, according to a report by the Jyllands-Posten newspaper.

Last year the project was approved by the Danish parliament. It is supposed to be built, owned - apart from the German land works - and operated by 4782 Femern A/S, a subsidiary of Sund & Bælt Holding, and financed by loans guaranteed by the Danish government.

Last June, the Danish government awarded €4.4 billion worth of contracts for initial Fehmarn Tunnel work to an international consortium that includes German Wayss und Freytag Ingenieurbau, Max Bögl Stiftung and Netherlands-based BAM.

Contracts include the excavation and construction of underground tunnels, manufacture of internal tunnel elements and the entry and exit ramps.

Last summer, newspaper reports suggested that work was expected to start in 2019 at the earliest, although it remains subject to approval by German authorities. Approval could come next year.

For more information on companies in this article

Related Content

  • EU launches investigation into Fehmarn Belt financing model
    June 21, 2019
    The European Commission said it will investigate the public financing for the Fehmarn Belt link to see if it in line with state aid rules. The announcement follows the European Union General Court's annulment of a previous Commission decision approving the support. "Today's opening of such an investigation is an invitation for all stakeholders to provide their input, which will allow the Commission to adopt a new, well-informed final decision,” said Margrethe Vestager, EU Competition Commissioner.
  • VIDEO: Drone for Fehmarnbelt tunnel
    August 1, 2025
    Dane Grace, one of the world's most talented drone pilots, has flown his drone over the German and Danish construction sites for the Fehmarnbelt Tunnel, set to be the world’s longest immersed tunnel.
  • Permanent Fehmarnbelt element factory?
    July 7, 2023
    Sund & Bælt has completed an environmental assessment of the tunnel element factory for the 18km Fehmarnbelt project between Denmark’s Lolland and Germany’s Fehmarn islands.
  • German government to adhere to Fehmarn Belt tunnel plans
    April 30, 2015
    Germany is to adhere to plans for a tunnel between Fehmarn, Germany, and Lolland, Denmark despite criticism over the cost and a delayed schedule. Denmark alone is likely to foot the €7.4 billion bill for the prestigious Fehmarn Belt Fixed Link immersed tunnel while Germany will pay for only access roads and other connections on its territory. Angela Merkel, Chancellor of Germany, said her government and transport authorities will respond to more than 3,000 objections over the construction of the tunne