Budimex consortium win Poland’s Ostroda ringroad court case

A district court in the Polish town of Olsztyn has ruled in favour of a consortium of Budimex and Ferrovial Agroman which challenged the awarding of a ringroad contract to a rival. The ruling means that the Salini consortium’s winning bid for the construction of a ringroad around Ostroda is overturned on the basis that it was ineffectually low. This means that the contract will go to the Budimex consortium which proposed to build the road for around €223 million. Polish builder Budimex is the consortium's m
March 18, 2015 Read time: 2 mins
A district court in the Polish town of Olsztyn has ruled in favour of a consortium of 3302 Budimex and 2717 Ferrovial Agroman which challenged the awarding of a ringroad contract to a rival.

The ruling means that the Salini consortium’s winning bid for the construction of a ringroad around Ostroda is overturned on the basis that it was ineffectually low.

This means that the contract will go to the Budimex consortium which proposed to build the road for around €223 million.

Polish builder Budimex is the consortium's main stakeholder, at 95%. The consortium must finish the work within 20 months from the contract signing.

Last December, the same Budimex and Ferrovial Agroman consortium announced it had won a tender to build a 22.6km section of the S3 express road between Silesian town of Legnica in the southwest and Lubin Poludiine, around 170km southeast of the capital Warsaw. The bid was nearly €220 million and construction is expected to take 30 months. Ferrovial Agroman is the engineering and construction arm of Spanish infrastructure group Ferrovial.

Earlier this year the Polish national roads authority 1361 GDDKiA said that it will no longer look for the cheapest offer in road-building tenders. Instead, it will, in line with 1116 European Union requirements, consider whole life cycle factors such as durability, cost of exploitation and quality.

Poland has long been criticised by the road construction industry, both within the country and in the rest of Europe, for handing out tender wins to the lowest bidder with scant regard for life-cycle costs. The government has also been heavily criticised for refusing to negotiate with winning contractors when unforeseen issue push up construction costs.

For more information on companies in this article

Related Content

  • Budimex and Strabag win 16km of Poland’s four-lane A1
    August 6, 2018
    Budimex and Strabag have won a contract to design and build 16km of Poland’s four-lane A1 highway between Tuszyn and Bełchatów. The €111 million deal with the Polish General Directorate for National Roads and Highways is scheduled for completion within 32 month, excluding winter months. The entire section will be concrete and includes two junctions, 17 bridges, several intersections and access roads, noise barriers and wildlife crossings.
  • Healthy bidding for Poland's highway construction
    May 14, 2012
    Bidding is healthy for a section of dual carriageway in Poland linking Kurow with Lublin. The section is 60km long and has been divided by the Polish General Directorate for National Roads and Motorways (GDDKiA) into five separate bids.
  • Astaldi begins drilling tunnels on Poland’s S7 dual carriageway
    March 14, 2017
    Italian contractor Astaldi has begun drilling two parallel tunnels as part of its S7 dual carriageway project in Poland. Each tunnel, between Naprawa and Skomielna Biala and under the Lubon Maly massif, will each be just over 2km long. Astaldi, based in Rome, won the three-year S7 dual carriageway project worth around €225 million in 2016 Work includes 38 bridges and viaducts and three motorway services. There will also be 25km of access roads and two junctions. The north-south S7, when complete
  • Polish road dispute
    February 28, 2012
    A string of legal and political battles look likely in the aftermath of a broken highway contract in Poland.