Budimex and Strabag win 16km of Poland’s four-lane A1

Budimex and Strabag have won a contract to design and build 16km of Poland’s four-lane A1 highway between Tuszyn and Bełchatów. The €111 million deal with the Polish General Directorate for National Roads and Highways is scheduled for completion within 32 month, excluding winter months. The entire section will be concrete and includes two junctions, 17 bridges, several intersections and access roads, noise barriers and wildlife crossings.
August 6, 2018 Read time: 1 min
3302 Budimex and 945 Strabag have won a contract to design and build 16km of Poland’s four-lane A1 highway between Tuszyn and Bełchatów.


The €111 million deal with the Polish General Directorate for National Roads and Highways is scheduled for completion within 32 month, excluding winter months.

The entire section will be concrete and includes two junctions, 17 bridges, several intersections and access roads, noise barriers and wildlife crossings.

“The A1 in Poland is an important link between the ports in the north of the country and the south of Europe. We are pleased to have again received an order for a section in the course of the expansion of the A1,” said Thomas Birtel, chief executive of Strabag.

For more information on companies in this article

Related Content

  • Road sector drives Europe’s construction recovery
    September 13, 2017
    Despite political concerns and upheavals, Europe’s construction market is on the up, reports Graham Anderson Europe’s road building market is forecast to grow strongly in real terms up to 2019, as a strengthening economy boosts construction, creating investment and jobs. The market is predicted to grow by 16% between 2016 and 2019 and is being led by increases in the UK (39%), Norway (38%) and Poland (35%). In the UK, the market is buoyed by a number of major projects coming on stream, such as England’
  • Legal battle for Croatia’s Peljeski Bridge contract continues
    April 19, 2018
    Only days after Croatia rejected initial complaints, contractors Astaldi, Ictas and Strabag said that they will submit new complaints over the Peljeski bridge winning bid. Croatian media report that Turkey's Ictas, Italy's Astaldi and the Austrian company Strabag are planning to submit a new complaint to the Croatian High Court against a decision by the state procurement authority DKOM to reject their previous complaints. At issue is the awarding of the Peljeski bridge and access roads project to the
  • Poland: Rubau Polska makes lowest bid in S61Via Baltica tender
    August 11, 2017
    Poland’s road authority GDDKiA said that five groups have tendered for construction of a 17.5km section of the S61 Expressway. The section runs from Podborze junction to Sniadowo junction and all bids fall within the investor's budget of around €146 million. The lowest offer reportedly was from a Rubau Polska consortium, at around €112 million, while the highest bid was lodged by Budimex at around €139 million.
  • New South Africa bridge project for STRABAG
    September 6, 2017
    Contractor STRABAG is to work on the project to build a new bridge connection in South Africa. This structure is of note as it will be Africa’s highest bridge at 223m high. The 1,132m long bridge will span the Mtentu River in eastern South Africa, close to the town of Flagstaff. The contract has a value of around €106 million and the construction work is expected to take 40 months to complete. STRABAG International is working with the South African contractor AVENG Grinaker-LTA on the project