Bosnia road corridor contract

The contract for the first stage of the Corridor 5C project for Bosnia has been signed. This 48km section of Corridor 5 will itself be constructed in four sections and is expected to cost more than €500 million. Funding for these four stages of the Corridor 5 project is being provided by the European Bank for Reconstruction and Development (EBRD) and the European Investment Bank (EIB), each of which will fund two stages.
March 21, 2019 Read time: 1 min

The contract for the first stage of the Corridor 5C project for Bosnia has been signed. This 48km section of Corridor 5 will itself be constructed in four sections and is expected to cost more than €500 million. Funding for these four stages of the Corridor 5 project is being provided by the 1166 European Bank for Reconstruction and Development (EBRD) and the 1054 European Investment Bank (EIB), each of which will fund two stages.

For more information on companies in this article

Related Content

  • Bosnia gets EBRD loan for Corridor 5c work
    January 8, 2024
    The project will include the construction of an interchange and a 15 km dual-carriage motorway section, along the Mostar North-South section.
  • Cengiz wins Corridor VC contract in Bosnia
    March 21, 2023
    Cengiz submitted the lowest bid in the tender which attracted three offers in the deal said to be worth around €361.8 million, according to Bosnia’s state highways agency Autoceste.
  • Construction delays affect Bosnian highway project
    May 10, 2012
    In Bosnia, delays have affected the construction work on the country’s key Corridor 5c highway project. So far 37km of the 336km Corridor 5c highway has been built, with 21km under construction and a further 43km section being cleared for work to commence. Construction work on a section of the Corridor 5c highway is set to commence by the end of September 2011. The section of highway being built is located in Ljubuska and Capljina, with work staring on the 4km Kravica-Bijaca and due for completion in 10 mon
  • €180 million for Bosnia highway
    July 6, 2012
    The EBRD is investing in the largest infrastructure project in Bosnia-Herzegovina (BiH) to date by lending €180 million to the state to construct key sections of the Trans-European Corridor Vc. A key transport artery linking BiH with the rest of Europe, Corridor Vc starts in Budapest, Hungary and ends in the Adriatic Port of Ploce in Croatia. It runs north to south through the centre of BiH, and is the most strategically important link for regional trade and economic development. The €180 million EBRD finan