Bosnia gets EBRD loan for Corridor 5c work

The project will include the construction of an interchange and a 15 km dual-carriage motorway section, along the Mostar North-South section.
By David Arminas January 8, 2024 Read time: 2 mins
European Corridor 5c – the backbone of Bosnia’s social and economic prosperity (image courtesy of Motorways of the Federation of Bosnia and Herzegovina - JP Autoceste FBiH)

The EBRD will provide a €110 million loan to Bosnia and Herzegovina for construction of the Mostar North-Mostar South section of pan-European Corridor 5c.

The project will include the construction of an interchange and a 15 km dual-carriage motorway section, the EBRD – European Bank for Reconstruction and Development said in a press release.

As well, the European Union will provide a €150 million grant through the Western Balkans Investment Framework (WBIF) and up to €150 million will be secured from local commercial banks for the project.

The WBIF is a joint initiative of the European Union, financial institutions, bilateral donors and the governments of the western Balkans. It provides financing and technical assistance to strategic investments in the energy , environment, social, transport and digital infrastructure sectors. It also supports private sector development initiatives.

The 700km Corridor 5c starts in the Hungarian capital Budapest, runs via northern Osijek in Croatia, through Bosnia and Herzegovina via Doboj, Zenica, Sarajevo and Mostar to end in the Croatian Adriatric port of Ploče.

According to the WBIF, Corridor 5c is the backbone of Bosnia’s connectivity – it has around 340km of the route – and is strategically vital for its economic development, making it a top priority for the Western Balkans regional development.

Bosnia’s Corridor 5c section is the first major motorway and the largest ever infrastructure project in the country´s history. More than 68km of motorway, including one cross-border bridge, have been supported by EU grants, blended with loans by European Bank for Reconstruction and Development as well as the European Investment Bank (EIB).

When work is done, the WBIF says that a typical journey from Sarajevo to the Adriatic Sea that now takes three and a half hours will be reduced to two hours.

Meanwhile, Bosnian media report that the 5.5km Poprikuše-Nemila section of 5c in Bosnia, originally scheduled for completion in May 2024, has experienced a delay and a significant cost increase. The project was initially contracted for €208 million.

However, the Turkish contractor, Cengiz Insaat, has been granted a further €27.2 million and an extension of 182 days due to unforeseen geophysical conditions encountered during construction.

For more information on companies in this article

Related Content

  • Bosnia project moves forward
    April 30, 2012
    Plans for work to a 150km section of the Corridor Vc highway in Bosnia will commence in 2012. Construction of 45km of the highway will be financed by the Government of Federal Bosnia, while the remaining 110km is due to be financed by foreign investors. The cost of the project has not been revealed at this stage. The plans were announced by Bosnia’s Ministry of Urban Planning.
  • Bechtel Enka opens first section of Pristina-Skopje motorway
    October 29, 2015
    The first part of the €600 million Arber Dzaferi motorway between Pristina, the capital of Kosovo and Skopje in Macedonia, has opened to traffic. US-Turkish consortium Bechtel Enka is contractor for the 60km road that will eventually link Pristina, capital of the former Serbian province Kosovo, and the city of Skopje, capital of Macedonia, a former Yugoslav republic. The road - numerically Route 6 – is Kosovo’s second motorway and is named after the prominent Albanian intellectual and politician from
  • EBRD funding for St Petersburg project?
    April 27, 2012
    The European Bank for Reconstruction and Development (EBRD) intends to provide a US$277 million (€200 million) loan to the Northern Capital Highway consortium, which will build the central 11.5km section of St Petersburg’s Western High Speed Diameter (WHSD) route. The EBRD’s board of directors has said will consider the loan on 14th February 2012. The finance package is of note as Russian road projects have largely found funds from other sources so far. The Northern Capital Highway consortium estimates the
  • Euroaszfalt and Duna Aszfalt in group to build 30km of stalled M4
    March 11, 2017
    A consortium that includes Hungarian firms Euroaszfalt and Duna Aszfalt has won the tender to construct a 30km section of the M4 motorway between Ullo and Albertirsa. Nearly €169 million will be invested in the project, according to Hungarian media. Other bidders were Kozgep of Hungary and Itinera of Italy. The M4 project is to link the Hungarian capital Budapest with Romania’s western border city of Oradea. The route will travel in Hungary through Cegléd – Szolnok – Karcag – Püspökladány – Berettyóúj