Australian state government does a deal with East West Connect

The state government of Victoria in Australia will pay the East West Connect consortium US$258 million to cancel construction of Melbourne’s East West Link road tunnel. The payoff is to cover the consortium's bidding, design and pre-construction costs and draw a line under the deal that has been mired in financial controversy for years. The federal government slammed Victoria’s decision to bail out of the project as “an obscenity’’ that will cost 7000 jobs, according to a report in The Australian news
April 15, 2015 Read time: 3 mins
The state government of Victoria in Australia will pay the East West Connect consortium US$258 million to cancel construction of Melbourne’s East West Link road tunnel.

The payoff is to cover the consortium's bidding, design and pre-construction costs and draw a line under the deal that has been mired in financial controversy for years.

The federal government slammed Victoria’s decision to bail out of the project as “an obscenity’’ that will cost 7000 jobs, according to a report in The Australian newspaper. Another $81 million in fees spent by the state government to set up a credit facility to borrow the project costs.

3260 World Highways has been following developments since October 2013 when the Victoria state government announced plans to build the East West Link, costed at the time between $5.64 and $7.53 billion.

Four consortia were shortlisted for the18km tolled motorway project: Momentum Infrastructure, consisting of Leighton, 4755 John Holland, Iridium and 4761 Dragados; Sicuro, made up of 2643 Egis, 236 Hyundai, 3149 Impregilo, Salini, Aquasia and InfraLinx Capital. The third consortium was Inner Link Group comprising 1304 Transfield Services, 930 Cintra, Samsung, 2717 Ferrovial, Ghella, 2378 Macquarie and REST. East West Connect, the eventual preferred bidder, is made up of Capella Capital, 976 Acciona, 979 Bouygues and Lend Lease.

But last month East West Connect said, after months of wrangling with the state government, that it definitely wanted out.

The government was wanting East West to payback around $153 million which the consortium allegedly received when the toll road contract was signed, reported the Herald Sun newspaper at the time.

The contract ran into trouble after a Victoria state election in November that saw a change in government. The incoming Labour Party administration of now premier Daniel Andrews brushed the deal aside, claiming the benefit to the state was only 45 cents for $1 spent to build the link.

World Highways reported last October that the consortium signed a contract with the Victoria government to deliver the US$7 billion, but only after the High Court rejected an application for an injunction to defer the controversial deal.

The project's winning design incorporates two 4.4km three-lane tunnels between CityLink and Hoddle Street. The consortium reportedly had spent nearly $35 million on the project up to the signing of the deal. The contract also included a $436.69 million kill fee to protect the consortium from sovereign risk.

Also in October, World Highways reported that Hyder and 2693 Parsons Brinckerhoff had been appointed as the design team for East West Link. The two engineering and management consultancies created a 50/50 joint venture to provide detailed design and construction support services for the 6.6km Stage 1 work, which is the eastern section, of the project.

Stage 1 was to be a three-lane road connecting the Eastern Freeway and CityLink, the majority of which will be underground in twin tunnels. The project's winning design incorporated two 4.4km three-lane tunnels between CityLink and Hoddle Street. However, the eastern section required extensive tunnelling to avoid disruption to suburbs, making it very expensive for what it would have delivered, especially given relatively low traffic volumes.

Andrews also said no preference would be given to the developers comprising the consortium regarding future projects. “Bids for future projects will be assessed appropriately and fairly under well-known principles and with a level of transparency that we just haven’t seen with this project,” he said.

For more information on companies in this article

Related Content

  • CPB Contractors closes deal for Melbourne’s West Gate Tunnel
    December 13, 2017
    CPB Contractors has achieved contractual close on Melbourne’s planned 5km West Gate Tunnel, originally called the Western Distributor. The road will link the West Gate Freeway at Yarraville, a suburb of Melbourne, with the tolled CityLink road network at Docklands via a tunnel beneath Yarraville.
  • VIDEO: Nexus picks up Toowoomba bypass project in Queensland, Australia
    August 21, 2015
    Nexus Infrastructure group has signed a contract with the Australian government to deliver the Toowoomba Second Range Crossing project in Queensland state, costing nearly US$1.2 billion.

    Nexus will design construct, finance, operate and maintain the 41km route that will bypass the city of Toowoomba, east to west.

    Toowomba and district, with a population of around 158,000, is inland 125km west of Queensland's capital city Brisbane, on Australia’s northeast coast.
  • Australia highway projects being planned
    November 24, 2015
    Key highway projects are progressing in Australia. In the state of Victoria, the authorities are planning a road widening project for the Monash Freeway that will cost an estimated US$289.54 million (A$400 million). The project calls for the route to be widened to five lanes in either direction for the stretch between the EastLink and the South Gippsland Highway.
  • New South Wales is seeking financial packers for WestConnex in Sydney
    June 19, 2015
    Investment bank Goldman Sachs will soon be sending out expressions of interest for backers to finance Australia’s biggest road deal, the three-stage WestConnex project to be rollout by the New South Wales government. According to a report by The Australian newspaper, initially around US$1.17 billion will be needed for the first phase of the Sydney toll road project. The first phase will likely cost between nearly $2.35 billion and $3.9 billion. Total cost of all three phases over 10 years could be as