Algeria cancels contractor’s construction contract

Japanese contractor Cojaal's contract for the construction of a stretch of Algeria’s East-West highway has been cancelled. The Algerian Ministry for Public Works terminated the contract as the firm had not met the requirements of the initial agreement when the deal was signed. The exact cause of this contract cancellation has not been revealed and nor is it clear if this development will bar the firm from tendering for future projects in the country. Much of Algeria’s East-West highway is complete but some
July 24, 2014 Read time: 2 mins

Japanese contractor Cojaal's contract for the construction of a stretch of Algeria’s East-West highway has been cancelled. The Algerian Ministry for Public Works terminated the contract as the firm had not met the requirements of the initial agreement when the deal was signed. The exact cause of this contract cancellation has not been revealed and nor is it clear if this development will bar the firm from tendering for future projects in the country. Much of Algeria’s East-West highway is complete but some sections remain incomplete. The quality of the work carried out by some of the parties involved in various sections of the project has been thrown into question. Algeria’s investment in transport infrastructure has been not insignificant and further highway projects are underway. However a number of firms have been barred from tendering for future works over poor performance on earlier projects.

Related Content

  • Contract problem for Algeria’s East-West Highway
    October 10, 2014
    Further problems surround the project to construct Algeria’s East-West Highway. Much of the route is complete, however a number of sections have faced delays with disputes having developed between contractors and the Algerian Government, which is overseeing the project. This latest development has seen the Algerian Ministry for Public Works announcing that the Japanese firm Cojaal has lost its contract to construct the remaining 84km of the eastern section of the East-West highway. It is not clear at presen
  • Cojaal’s Algeria road contract restarting?
    October 7, 2015
    In yet another reversal for a key Algerian road project, the Algerian Government has overturned its earlier decision to cancel Cojaal’s contract. The Algerian Government opted to change its 2014 decision to cancel a contract with Japanese construction company Cojaal. The project is for Algeria’s massive East-West highway, for which Cojaal was working on an eastern stretch. Talks are being carried to reach an agreement with Cojaal, which was initially awarded the contract to build a 399km stretch of motorway
  • Algeria East-West Highway opening due
    September 9, 2015
    The long running saga of Algeria’s East-West Highway should come to a key point soon, when most of the route will finally be open to traffic. The 1,216km-long route will be fully operational at the end of October 2015. This is of course with the exception of the Lakhdaria section, which still requires rehabilitation work to be carried out. The repairs are expected to carry on until May or June 2016. Contractors from all over the world have been involved in the East-West highway project but certain stretches
  • Algeria to engage Japanese government over dispute with Cojaal
    January 14, 2015
    The Algerian government is now talking directly to the Japanese government in an effort to resolve a dispute with sacked Japanese highways consortium Cojaal, In 2006, Cojaal won a US$5 billion deal to build the 359km eastern section of Algeria’s proposed 900km East-West Highway within 40 months. Algeria divided the contract into three sections, with the Chinese company Citic-CRCC winning the central and western sections, which in total was to cost around $6 billion.