Kenya port suspension bridge project makes progress

A new suspension bridge in Kenya’s key port city, Mombasa, will help unlock potential – Shem Oirere reports Plans for the construction of a US$200 million suspension bridge in Kenya heva moved a notch higher. The country's urban roads agency recently announced the shortlisting of three bidders for the design, finance, construct, operate, maintain and transfer public private partnership (PPP) contract model. Kenya Urban Roads Authority (KURA) is a state agency that manages, develops, rehabilitates and mai
January 15, 2019 Read time: 4 mins
Mombasa’s busy port will benefit from the new suspension bridge connection
A new suspension bridge in Kenya’s key port city, Mombasa, will help unlock potential – Shem Oirere reports


Plans for the construction of a US$200 million suspension bridge in Kenya heva moved a notch higher. The country's urban roads agency recently announced the shortlisting of three bidders for the design, finance, construct, operate, maintain and transfer public private partnership (PPP) contract model. 6679 Kenya Urban Roads Authority (KURA) is a state agency that manages, develops, rehabilitates and maintains national urban trunk roads. And Kura announced in late October the shortlisting of Nyali Connect Consortium, IHI-Join-Acciona Consortium and Strabag AG for the 2nd Nyali Bridge Public Private Partnership project in the country's second biggest city of Mombasa.

Nyali Connect Consortium includes Vinci Highways, Meridiam and Vinci Concessions while IHI-Join-Acciona is a consortium of Japan Overseas Infrastructure Investment Corporation for Transport and Urban Development and Acciona. Other bidders that had responded to KURA's Request for Qualification were China Communication Construction Company and a consortium of Mota Engil Africa, AIIM, Egis and Orascom.

“It is the qualified firm that the government will get into a deal with. We want to start negotiations and see who can offer the best deal from the three,” KURA Communications Officer John Cheboi told Business Daily in early October.

KURA's Manager for Transport Economics Richard Kyalo said previously that the interest by five reputable international infrastructure firms in developing the bridge “is a sign of strong interest by the market on the project and a mark of confidence in the procurement process.”

The option of the PPP model for constructing the bridge is a strategy by Kenya to mobilise private capital and leverage private sector efficiencies and innovation in delivery of key infrastructure projects outlined in the country's economic blueprint, Vision 2030.

The 2nd Nyali Bridge project is one of those listed under Kenya's PPP Programme and are at various stages of development. By June 2018, there were 72 PPP projects in the pipeline, 67 of which were approved under the solicited process and five approved as Privately Initiated Investment Proposals, according to Kenya's National Treasury.

The preferred bidder will construct a 600m suspension bridge over the Tudor creek to connect Mombasa Island to Mombasa Northern mainland through the Nyali region. The bridge will be tolled with a six-lane dual carriageway having three lanes on either side.

The bridge, which is to be constructed 500m to the south of the existing Nyali bridge, will have steel carriageway beams supported through hangers from two main cables.

KURA says in a project brief that was prepared by Transaction Advisors Deloitte East Africa & India, Iseme Kamau & Maema Advocates, Cliffe Dekker Hofmeyer, HP Gauff Ingenieeure and Earth Care Services with financing from the World Bank, the contractor will, after raising financing, produce the designs, constructed and managed the bridge,  “get compensation from end user charges collected by the government on its behalf.”

The location of the suspension bridge, which is set to be second longest in Africa, was largely picked because the route “has the highest vehicular traffic and therefore must be critical in unlocking perennial traffic gridlocks in and around Mombasa city.”

Associated with the bridge project is the construction of 1.7km of new roads and expansion of 5km of existing roads.

The existing Nyali Bridge, which was built by the Japanese in 1979 is characterised by heavy traffic congestion, with nearly 46,000 daily vehicle trips, a large share originating from Mombasa central business district (CBD). The speed on the route has been reduced to 6km/h especially during morning and evening rush hour, with KURA indicating the bridge is nearing its design capacity of 50,000 vehicle trips/day at a time when the population of Mombasa has more than doubled in the last 39 years to 800,000 from 341,000 in 1979.

“A new bridge to the south of the existing Nyali Bridge would yield the greatest traffic benefits, in terms of traffic operations and capacity, attracted volumes, travel time savings and network connectivity,” according to the project brief.

The County Government of Mombasa has previously said the new bridge can form a large ring road covering Kongowea and the Island’s peripheral areas, avoiding major pedestrian traffic hubs, hence reducing the intensity of vehicular congestion.

KURA could not immediately confirm when the successful bidder will be announced although the project is behind schedule according to an earlier implementation plan. The plan envisaged the notice of contract award to be given in November 2017, with signing of the contract agreement in the same month. Financial close for the bridge project was expected in March of 2018.

For more information on companies in this article

Related Content

  • Temporary bridge replacement in the US
    July 2, 2019
    A temporary bridge structure provided by Acrow Bridge is maintaining traffic flow for a key crossing in Vermont. The bascule bridge is allowing both vehicular and vessel traffic to pass during the reconstruction work to the North Hero-Grand Isle Drawbridge in Vermont. The US$60 million project involves replacing the historic twin leaf bascule bridge on Lake Champlain. This modular steel bascule bridge is allowing transport to continue to and from the Lake Champlain island towns of North Hero and Grand Isl
  • Canada: work officially starts on Montreal’s Champlain Bridge
    June 25, 2015
    Canada’s infrastructure minister, Denis Label, officially broke ground for Montreal’s replacement Champlain Bridge, saying the project will likely cost US$3.42 billion. The 3.4km Champlain Bridge Corridor Project, including spans and highway expansions, is expected to be completed by 2019. SNC-Lavalin, the 50% stakeholder in the winning consortium Signature on the Saint-Lawrence, recently announced it had finalised the deal with new Champlain Bridge owner Infrastructure Canada. Signature on the Saint-
  • Ghana moves to reduce Accra’s road pollution and congestion
    August 28, 2019
    The west African country of Ghana has commissioned a traffic management centre to alleviate chronic congestion and drastically reduce vehicle pollution in the capital Accra. Nana Akufo-Addo, Ghana’s president, welcomed the opening of the centre, saying the increase in traffic “coupled with rapidly increasing urban population is putting a lot of pressure on facilities in our cities, especially on our road infrastructure and also sapping productivity”. The centre, which local media claim is the first of
  • Galliford Try aims to downsize its construction business
    April 25, 2019
    UK construction and infrastructure business Galliford Try is reviewing its construction business with a view to downsizing. “The review will reduce the size of the construction business, focusing on its key strengths in markets and sectors with sustainable prospects for profitability and growth, where we have a track record of success,” the company said in a written statement. “The board anticipates that this review will result in reduced profitability in the current year reflecting a reassessment of