Tough truck linings for Brazil quarry

In Brazil the Julio and Julio Group is now using Metso's Haul Truck Solution to reduce the operating costs and improve the performance of its truck fleet in the São Domingos quarry in Sorocaba. Over the long term, this investment is estimated to reduce operating costs by 30%. The São Domingos quarry has a capacity of about 1,200,000tonnes/year of crushed stone and covers an area of 1,500,000m² in Sorocaba, São Paulo state. Julio and Julio was looking for a hauling solution that meets current market specif
April 16, 2018 Read time: 2 mins
In Brazil the Julio and Julio Group is now using 6934 Metso's Haul Truck Solution to reduce the operating costs and improve the performance of its truck fleet in the São Domingos quarry in Sorocaba. Over the long term, this investment is estimated to reduce operating costs by 30%.


The São Domingos quarry has a capacity of about 1,200,000tonnes/year of crushed stone and covers an area of 1,500,000m² in Sorocaba, São Paulo state. Julio and Julio was looking for a hauling solution that meets current market specifications, utilises the latest technology, and adheres to environmental legislation.

"The high-performance rubber truck lining solution will give the quarry greater maintenance flexibility, reduce fleet downtime and increase productivity," said Ricardo Bonadia, industrial manager of the Julio and Julio Group. "We are looking for a reduction in our operating costs. The Metso solution meets our needs and is an industry benchmark.

The lining installed on trucks maximises fleet availability and productivity, reduces noise during loading and unloading, improves driver comfort and maintains truck suspension. The perceived noise is reduced by 50% or more and the shocks and vibrations by 95%. Another advantage of Metso's rubber truck lining is its modular composition. When replacement is required, only the worn modules have to be changed.

Bonadia also highlighted the wear life of the truck linings as these rubber products typically last four times longer than steel linings.  "Before, we used steel plates that had a wear life of about 2,000 hours, and the truck required a 2- or 3-day maintenance stoppage due to the number of welds. Avoiding this was one of the key factors when choosing Metso's Haul Truck Solution," Bonadia said.

For more information on companies in this article

Related Content

  • Reducing plant noise
    February 7, 2012
    German quarrying firm Oetelshofen Kalk has cut noise emissions by half and tripled machine service life, by installing dual hardness rubber liners in its crushing plant. Based in Wuppertal, the Oetelshofen quarry company produces 2 million tonnes of limestone products/year, and has a turnover of €35 million/year.
  • Long life and reliability from innovative crusher
    July 9, 2012
    New technology broadens Sandvik's offering for crushing and screening. Mike Woof reports Sandvik is making a series of upgrades to its crushing and screening line in jaw and cone crushers as well as wear parts, and these should suit an array of applications ranging from small recycling operations up to large quarry sites. At the more versatile end of the range is the new CJ208 jaw crusher, the latest addition to the CJ200 series jaw crusher line-up. This crusher is the smallest of the CJ200 Series and offer
  • Innovations in aggregates production will boost quarry efficiency
    March 16, 2016
    New innovations are underway that will help optimise rock crushing and screening operations and boost quarry efficiency overall - Mike Woof writes. Quarrying is a tough industry that provides enormous challenges to equipment providers as machines and technology have to be rugged, durable and productive. Cutting the cost of production while optimising output has been a major target for suppliers, with new technologies playing an increasingly important role. Taking the long view with regard to increased qu
  • Sandvik's 'quiet' quarry solution
    February 6, 2012
    A Hanson quarry in Spain is now benefiting from the installation of lining plates in its crushing plant. The J Riera, Llinar del Valles Quarry in Catalonia is using WT6000 linings supplied by Sandvik in the plant's primary hopper. The material was chosen for this tough application as the quarry company wanted to reduce wear and tear on its equipment and cut noise from the site. The hopper is the main intake for feed material in the plant and the rock is blasted granite, with a high abrasive index and a maxi