Lochkov bridge construction time 'cut'

As part of the R1 southern orbital motorway around the Czech capital, Prague, a joint venture is building a five-span, 461m long and approximately 65m high viaduct near the village of Lochkov, as a girder bridge construction. For the two steeply inclined twin piers, Doka has supplied an automatic climbing formwork solution that obviates the need for shoring and that will "cut more than 100 days from the construction period." Cast-in-place concrete construction of bridge piers with such a steep inclination
July 17, 2012 Read time: 3 mins
Inclined at 33° from the vertical, these upwardly widening twin piers are being erected using Doka formwork
As part of the R1 southern orbital motorway around the Czech capital, Prague, a joint venture is building a five-span, 461m long and approximately 65m high viaduct near the village of Lochkov, as a girder bridge construction.

For the two steeply inclined twin piers, 203 Doka has supplied an automatic climbing formwork solution that obviates the need for shoring and that will "cut more than 100 days from the construction period."

Cast-in-place concrete construction of bridge piers with such a steep inclination usually requires a large volume of heavy falsework: there are not only vertical loads to be transferred but horizontal loads as well, and there has to be a standing space for the falsework on the valley floor which is capable of supporting the loads involved.

"No wonder, then, that when it came to planning the two twin piers of the Lochkov Bridge south of Prague, with their 57° inclination (33° from the vertical), the Doka Formwork experts' suggestion of using a self-climbing formwork solution was received by the JV with open ears," says Doka.

The rule is, says Doka, that when concreting inclined cross-sections, allowance must be made not only for the loads from the pouring operation but also for an inclination-dependent share of the concrete weight. This makes the statistical calculations more complex. On the Lochkov Bridge, the design of the twin piers provides for a precast intermediate slab, with in situ concrete topping, after every other 2.1m high casting section.

It was found that it would be possible to make use of this intermediate slab to relieve the self-climbing system of a significant part of the concrete weight by way of specially designed sets of inside formwork for the piers.

Made up of only around 142m² of Doka large-area formwork Top50, the four inside formwork units transfer the bulk of the additional loads into the lower casting sections. Their 4.2m height corresponds to two casting sections, meaning that the inside formwork only needs to be lifted and reset in every other climbing step, which saves crane time.

On each pier, the 2.1m high Top50 outside formwork is climbed by ten vertically parallel units of Doka climbing formwork SKE 50 with a load capacity of 5tonnes per bracket (four units on the forward-inclined side and six on the overhanging side).

For more information on companies in this article

Related Content

  • Modern formwork systems - fast, flexible, safe
    February 21, 2012
    Speed of erection, safety, cost-efficiency and flexibility are among the attributes of modern formwork systems. Modern formwork and scaffolding systems are attractive in particular for their speed of erection, safety, cost-efficiency and flexibility.
  • Doka delivers cantilevering for super-slim piers at Lahntal Bridge
    October 21, 2016
    Doka’s formwork expertise is currently in demand during the construction of one of the busiest motorway viaducts in Germany. The 400m six-lane Lahntal Bridge in Limburg dates from the early 1960s. Every day about 100,000 vehicles cross the bridge that spans the valley of the River Lahn. But traffic loads have increased sharply, so a new bridge is being built sited just a few metres west of the old viaduct. The new Lahntal viaduct will measure a massive 43.5m in width, enabling eight lanes plus hard shoul
  • Challenging viaduct construction
    March 2, 2012
    TRAFFIC VOLUMES on Gran Canaria, the third largest of the Canary Islands, have been swelling rapidly in recent years, not least because of the boom in tourism. Among the routes most affected is the 32km long northern motorway GC-2 between Las Palmas and Agaëte, which has reached the limits of its capacity.
  • Innovative formwork solution to bridge construction
    February 20, 2012
    Innovative solutions are being applied to the construction of bridge structures as Patrick Smith reports. RMD Kwikform Iberica has engineered and supplied specialist formwork and falsework for construction of the much-needed Monteporreiro Viaduct in northern Spain. The viaduct will connect Monteporreiro with the Benedictine Monastery of San Bieito Lérez on the other side of the river, and in the process will ease congestion in the nearby town of Pontevedra, diverting some 5,000 vehicles/day.