Skip to main content

Asphalt paving innovation from Aggregate Industries

The firm developed this new surface course in a bid to match increasing traffic volumes on the UK’s road network. According to Aggregate Industries, this material can speed up road surfacing by more than 40%. There is a major need to repave many UK roads, with the country’s vehicle population having increased by 10 million in the last 10 years. This has triggered an increased need for infrastructure maintenance. But the time needed to carry out road repairs can cause major problems for motorists.
October 20, 2017 Read time: 2 mins
A low-temperature asphalt solution has cut paving time on a trial project in the UK

The firm developed this new surface course in a bid to match increasing traffic volumes on the UK’s road network. According to 2297 Aggregate Industries, this material can speed up road surfacing by more than 40%. There is a major need to repave many UK roads, with the country’s vehicle population having increased by 10 million in the last 10 years. This has triggered an increased need for infrastructure maintenance. But the time needed to carry out road repairs can cause major problems for motorists. The latest solution from Aggregate Industries is a low-temperature, 20mm, SuperFlex surface course that can be laid in a single layer at depths between 100mm and 130mm to achieve a minimum surface texture.

The SuperFlex surface material removes the need for two separate treatments, a binder course and surface course, delivering pavement treatment in one, saving money and time.

Aggregate Industries trialled the new SuperFlex in March 2017, resurfacing the A3 Kingston Bypass, one of the busiest roads in South London, as part of the London Highways Alliance Contract (LoHAC). The trial saw SuperFlex help reduce the time needed to complete the project by 55%.

Martin Freeman, Area Manager for the South East Contracting at Aggregate Industries said, “By using the new 20mm Superflex instead of a traditional course pavement treatment, the team delivered an astounding 43% time-saving. This allowed the contracting team to surface an average of 600tonnes/night – with an unprecedented 700tonnes surfaced on 15th March.

For more information on companies in this article

Related Content

  • Stiffer roads, less fuel?
    October 19, 2020
    Researchers at the Massachusetts Institute of Technology looked at how much fuel – and, hence carbon – could be saved by making roads in the US stiffer. They concluded that by resurfacing 10% of roads every year for the next 50 years, 0.5% of total transport emissions, or 440 megatons, would be saved over that period.
  • World growth in geosynthtics set to rise
    February 17, 2012
    With geosynthetics sales set to grow rapidly in the next three years, manufacturers are preparing for the demand. Patrick Smith reports. Global demand for geosynthetics is projected to increase 5.3% annually to 4.7 billion m² in 2013 with countries such as China, India and Russia expected to post the strongest gains through the forecast period. All are building large-scale infrastructure developments and face evolving environmental protection regulations and strict building construction codes.
  • The cycle of potholes in the UK
    May 9, 2019
    Since 2015 almost a million potholes have been recorded annually by UK local authorities, with the 2016 count reaching 1,088,965, according to an insurance provider. The Insurance Emporium obtained data from 175 local authorities and compared it to the incidence of injury and damage claims made against these authorities by cyclists. During 2017-18, there were 335 pothole damage and injury claims filed against local authorities. Personal and dental injuries to cyclists accounted for 16% of these and d
  • LafargeHolcim delivers Algeria concrete road solution
    May 14, 2018
    In Algeria, LafargeHolcim has introduced roller compacted concrete (RCC) for the first time in the country to renovate the RN45 road, with reduced costs, construction time and increased durability - *Nicolas Miravalls. Heavy traffic on a road stretch in northern Algeria has resulted in the need for rebuilding of the link, making it better able to cope with demand. In Algeria’s Msila region, the RN 45 road carries over 700 heavy load trucks/day, 365 days/year and required a major re-construction. In 2017, La