Skip to main content

STRABAG wins tricky Polish project

Austrian construction firm STRABAG has won a major road contract from Poland’s General Directorate for National Roads and Highways (GDDKiA). The deal is for the construction of a 40km section of the S8 Expressway between Walichnowy and Sieradz Poùudnie, some 240km to the south west of capital Warsaw.
March 21, 2012 Read time: 2 mins
Austrian construction firm 945 Strabag has won a major road contract from Poland’s General Directorate for National Roads and Highways (1361 GDDKiA). The deal is for the construction of a 40km section of the S8 Expressway between Walichnowy and Sieradz Poùudnie, some 240km to the south west of capital Warsaw. The contract is worth some €254 million and the work is now starting and expected to take some 27 months to complete. It is worth noting that concrete construction will be used for the S8. The work is being carried out in two stretches and the 19km section of S8 between Walichnowy and Zùoczew is for four lanes and includes construction of a junction with the busy National Road 45 as well as 16 bridges. Due to difficult geological conditions, the area will require a total of 60,000m of piles and 700,000m³ of geotextiles. The construction work will be carried out by local subsidiaries 2861 Hermann Kirchner Polska, STRABAG Sp and Heilit+Woerner Budowlana. The firm’s bid of €157.4 million was the lowest out of the eight submitted in the tender. Other bidders included 3414 Shanghai Urban Construction Group and the consortia of: 3305 Polimex-Mostostal, Pol-Aqua and PBG. The second section between Zùoczew and Sieradz Poùudnie is 19.6km long and features two lanes, again using concrete technology. The section also requires the construction of 18 bridges, the conversion of local and municipal roads, as well as the construction of the Dàbrowa Wielka rest area including the technical infrastructure. The works are being carried out by a consortium of STRABAG Sp and Heilit+Woerner Budowlana. “The difficult subsoil conditions of this project represent a special challenge: our great experience and our technical know-how in this field afforded us a decisive advantage and allowed us to secure the contract,” said STRABAG SE CEO Dr Hans Peter Haselsteiner. In all GDDKiA has signed contracts for the construction of four sections (2,3,4 and 5) of the S8 road, which measure a total length of over 78km. The value of the contracts is close to €620.6 million.

Related Content

  • Inter-oceanic Corridor for Brazil-Bolivia-Chile
    March 2, 2015
    A new Bolivian link is playing a key role in a major Latin American highway – Mauro Nogarin reports. Construction of a new route through Bolivia will help deliver improved transport between Latin America’s Pacific and Atlantic coasts. The construction of the highway between Santa Barbara-Caranavi-Quiquibey has been carried out by the consortium ARBOL. This firm is a partnership between the Argentinean company Grupo Eling and Administradora de Caminos Boliviana (ABC). The stretch of highway is an important s
  • Inter-oceanic Corridor for Brazil-Bolivia-Chile
    March 2, 2015
    A new Bolivian link is playing a key role in a major Latin American highway – Mauro Nogarin reports. Construction of a new route through Bolivia will help deliver improved transport between Latin America’s Pacific and Atlantic coasts. The construction of the highway between Santa Barbara-Caranavi-Quiquibey has been carried out by the consortium ARBOL. This firm is a partnership between the Argentinean company Grupo Eling and Administradora de Caminos Boliviana (ABC). The stretch of highway is an important s
  • Abu Dhabi deal due
    May 25, 2012
    Abu Dhabi’s Department of Transport plans to announce the winner of the US$2.7 billion Mafraq-Ghweifat highway project in the fourth quarter of this year. The 327km highway will connect Saudi Arabia and the UAE and this project will be the first transport public-private partnership (PPP) project in the region. Bidders include China Communications Construction Company, Austrian firm Strabag and Australian company Macquarie. Abu Dhabi’s Department of Transport says that the project is still undergoing final a
  • Super paving with Aggregate Industries’ SuperThin
    February 21, 2019
    Aggregate Industries’ contracting division recently laid a total of 1,800 tonnes of an ultra-low noise asphalt at Brampton Hut Services in Huntingdon in one weekend. Section 1 of Highways England’s A14 Cambridge-to-Huntingdon Improvement Scheme will see 21km of the road upgraded to three lanes in each direction and is expected to cut journey times by up to 20 minutes. The pavement works at Brampton Hut motorway services specified minimum sound level requirements of -7.5db (A). The limits are designed