Skip to main content

Rising to the challenge

Visualise today's concept of a major commercial traffic corridor in the western United States. A roadway responsible for delivering goods to Arizona, Nevada and Utah, that also connects Mexico to the United States to Canada through the North American Free Trade Agreement (NAFTA). What springs to mind? A multi-lane highway carrying thousands of vehicles a day past cities at speeds up to 113km/hour, while egress ramps make sure vehicles get safely to city streets and their final destination. This is not the c
July 18, 2012 Read time: 6 mins

Visualise today's concept of a major commercial traffic corridor in the western United States. A roadway responsible for delivering goods to Arizona, Nevada and Utah, that also connects Mexico to the United States to Canada through the North American Free Trade Agreement (NAFTA).

What springs to mind? A multi-lane highway carrying thousands of vehicles a day past cities at speeds up to 113km/hour, while egress ramps make sure vehicles get safely to city streets and their final destination.

This is not the case with a vital stretch of U.S. Highway 93 connecting Arizona to Nevada.

It is a major commercial corridor with very little modern-day design, making it an adventure for the 14,000 vehicles/day travelling the narrow lane two-lane highway atop the Hoover Dam packed with thousands of sightseers. It is also potentially dangerous.

For many of these reasons, U.S. 93 was considered a high priority corridor for modernising by the National Highway System Designation Act of 1995. Funding for the $240 million bypass reflects the joint federal-state coalition and commitment to the project and includes: $100 million in federal funds from various programs; $20 million each from the States of Arizona and Nevada; and $100 million in bonded funds.

The attacks on the Twin Towers of 11 September, 2001, served to fast-track the need for a bypass, as commercial trucks were no longer permitted to use U.S. 93 to cross the dam.

"Only those trucks authorised through a local permit programme for local business are allowed to cross," explains Dave Zanetell, Project Manager for the 2410 Federal Highway Administration (FHWA).

The current alternate route to cross from Nevada to Arizona for commercial truck traffic is through Laughlin, Nevada, which adds 27km to the trip.

Bypass underway

Following extensive environmental impact studies, careful consideration of the best location for the bypass, and significant public feed-back during the late 1990s and early 2000s, design for the Hoover Dam Bypass project began in 2001.

The 2408 Central Federal Lands Highway Division of the FHWA manages bypass design and construction and leads a high-level Project Management Team (PMT) consisting of the FHWA, the States of Nevada and Arizona, the 2413 Bureau of Reclamation, the 2407 Western Area Power Administration and the National Parks Service.

The PMT chose Sugar Loaf Mountain for the bypass alignment, determining this route had the least environmental impact and was the most economically feasible of the three alternatives considered.

The 5.6km bypass corridor for U.S. 93 starts in Clark County, Nevada, and ends in Mohave County, Arizona.

A focal point of the project, the bypass bridge crosses the Colorado River at Black Canyon some 488m south of the Hoover Dam. Matching the magnificence of the dam, a composite bridge design with a steel superstructure and concrete arches was selected by the PMT.

The chosen design enables on-site work to progress concurrently with precasting and steel fabrication activities, while offering the greatest flexibility to design and construct the most cost-effective elements for bridge components.

Construction of the 579m Colorado River Bridge began in early 2005 by a joint venture between 2401 Obayashi Corporation and PSM Construction, USA.

"On a project of this magnitude, a joint venture works best for bonding and to share the risk," says Terry Pawlowski, Project Engineer for Obayashi/PSM JV.

The best from all of the JV's employees is what will be required to construct the bridge. Just the sheer height above the river (approximately 274m) poses its own set of issues.

"Access to the work and getting equipment to the site are big challenges," says Pawlowski.

Excavation and blasting the steep Sugar Loaf slopes for pier footings was difficult, since the contractor had to ensure that excess material did not fall into the Colorado River.

Once on site, equipment and supplies must get to the workers on the bridge deck, piers and arches. To address this Obayashi/PSM constructed a high line that spans the canyon. This critical tool allows equipment and material to be delivered over the canyon to where it is needed.

Ambient conditions also play a factor in constructing the Colorado River Bridge. The weather can bring extreme temperature swings, rain and sometimes snow during the winter months, while the summer months can feature long stretches of temperatures well over 37°C.

When is comes to paving the bridge deck, Obayashi/PSM pays close attention to the wind speed, as the contractor does not want the surface to dry too quickly.

"We target paving when the wind is blowing 16km/hour or less," says Pawlowski. The company will not pave if the wind tops speeds of 24km/hour and has learned the best times to pave. "The wind regularly dies down at night, so we are paving during the night-time hours."

Built for the future

With the inherent risks associated with constructing the bypass, the PMT is having the contractors build the approaches and bridge to easily handle the current 14,000 vehicles/day load as well as future traffic demand. The bridge, which will feature a pedestrian walkway and shoulders, will have a total deck width of 26.8m.

With the challenging paving conditions, Obayashi/PSM is paving the deck full width, using a Bid-Well 4800 bridge paver. With a 121.9cm truss depth to prevent deflection across the span, the 4800 was equipped with two Rota-Vibe carriages, one each to pave the northbound and southbound lanes up to a centre barrier.

Being delivered by a concrete pump truck at a 10-15cm slump, the deck's 4500 PSI concrete includes a fibre mesh to help control surface cracking. Aiding in concrete curing, the 4800 paver's finishing pans were equipped with an optional fogging system to immediately initiate the moist cure.

Obayashi/PSM decided to pour the pedestrian walkway at the same time as the traffic lanes, so the paver was equipped with an optional sidewalk roller.

"The sidewalk roller allows us to pour the full deck width at one time, rather than going back to pour and hand screed the sidewalk after finishing the traffic lanes," explains Pawlowski Working high above the Colorado River, the contractor is also extremely concerned about worker safety. There is not a lot of room for workers finishing the sides of the deck. The overhang jacks support a walkway enclosed by steel railing and a handrail marked with safety tape. All workers also attend a safety meeting prior to working on the job site.

Beginning on 10 April year, Obayashi/PSM paved the deck over the first five piers on the Nevada side of the bridge and piers 14 and 15 on the Arizona side. A total of seven pours were made, totalling nearly 1,758m3 of the nearly 4,205m3 necessary to complete bridge deck paving.

With these pours complete, the contractor has now stopped deck paving and is focused on completing the bridge's arches. It will take approximately 14 months to complete the 323m spans of the twin concrete arches, which will be the longest in the Western Hemisphere.

Once the arch work is complete, the contractor's attention will once again focus on the bridge deck. Obayashi/PSM will have to carefully pour the final bridge sections.

"We have to load the arch symmetrically from the centre out," says Pawlowski.

Even with these extreme challenges, the JV is confident it will be up to the task to complete work by the 2010 deadline.

Related Content

  • Terex built for bridge paving
    November 29, 2012
    To meet a need to carry out complex modern bridge designs, the Terex Bid-Well 3600 paver is available with truss transition inserts, increasing maximum paving width from 27.4-33.5m. The inserts adjust truss depth from 914-1219mm toward the paver’s centre, reducing frame deflection and this is said to increase surface profile smoothness. Offering paving widths from 4.6-33.5m with optional transition inserts, the 3600 gives companies more versatility for paving a wide variety of bridge designs, including mult
  • Bridge and tunnel concrete testing vital for longevity
    July 9, 2012
    Modern technology is making testing more efficient and reliable, increasing productivity and reducing costs, as Patrick Smith reports A few years ago, visual inspection of an 18-year-old bridge by ARRB in Australia identified considerable cracking in the precast, prestressed deck planks as well as in the cast in situ deck overlay. Laboratory examination indicated that the deck planks and the deck overlay were suffering from a strong case of alkali-aggregate reaction (AAR). Testing of concrete cores drilled
  • Brazilian contractor uses novel methods for high quality road
    January 5, 2015
    Cold-in place recycling method provides fast road rebuild in Brazil In Brazil a road contractor has carried out a high quality road rebuilding job, using novel techniques. Contractor Brown Brown is located in Santa Teresinha in the state of Bahia and recently carried out a two-week job for the company to rehabilitate sections of highway BR-381. The highway is an important route in Brazil and runs from Sao Paulo to Belo Horizonte. Highway BR-381 or Rodovia Fernão Dias, as it is called, stretches some 576km
  • RMD formwork for Qatar’s tallest bridge on Doha East Corridor
    July 6, 2016
    RMD Kwikform will be supplying tens of thousands of tonnes of its formwork and shoring for construction of Qatar’s tallest bridge on the Doha East Corridor project As well as the bridge, the Corridor contract comprises four interchanges at a total cost of US$612.5 million. Ashghal, Qatar's Public Works Authority, awarded the Corridor project to China Harbour Engineering Design and Construction. Built as a five-lane 11km bypass in Doha, the capital of Qatar, the project will also cater for a rail line