Mini-bridge aids Forth repairs

An engineering "first" means that rehabilitation work on a vital Scottish bridge built over 40 years ago can be carried out smoothly A new report to the Forth Estuary Transport Authority (FETA) in Scotland recommends appointing Balfour Beatty Civil Engineering of Edinburgh as 'preferred bidder' to carry out the scheduled replacement of the bridge's main expansion joints in 2009. However, the report to the bridge authority says the tender price of £13.7 million (US$21.3 million) is some £5 million ($7.8 mill
July 17, 2012 Read time: 4 mins

An engineering "first" means that rehabilitation work on a vital Scottish bridge built over 40 years ago can be carried out smoothly

A new report to the 4069 Forth Estuary Transport Authority (FETA) in Scotland recommends appointing 1146 Balfour Beatty Civil Engineering of Edinburgh as 'preferred bidder' to carry out the scheduled replacement of the bridge's main expansion joints in 2009.

However, the report to the bridge authority says the tender price of £13.7 million (US$21.3 million) is some £5 million ($7.8 million) higher than had been budgeted for, so cost savings or reallocation of funding will be required before the contract can be awarded.

Chief Engineer and Bridgemaster Barry Colford said: "We engaged an experienced firm of consulting engineers to estimate the cost of this job, but the disparity between their estimate and the actual bids demonstrates just how unpredictable the costs of carrying out maintenance works on large bridges without major disruption to traffic can be.

"This job in particular is unique so there's very little to compare it to. The joints we are replacing are the oldest and largest of their kind in Europe and to keep the traffic flowing during the works we have come up with an engineering solution that is a first for a major suspension bridge." When opened in 1964, the bridge (2.5km with approach viaducts) was the longest suspension bridge outside the USA, but now its traffic loading is much higher than predicted.

The main expansion joints on the bridge (which spans the Firth of Forth connecting the capital Edinburgh with North Queensferry, Fife) allow the suspended roadway to expand and contract, and have already exceeded their expected service life.

The work is due to be carried out in two phases of ten weeks in Autumn 2009 and early 2010. In order to minimise disruption to traffic, engineers plan to construct temporary mini-bridges on the surface of the bridge to lift traffic up and over the work areas while replacement is carried out. This would mean that two lanes in each direction remained open, although closures will be required to construct and dismantle the temporary bridges.

The custom-built temporary bridges will be significant structures in their own right, measuring at least 80m long and over 2m high. They will be positioned under each of the bridge's main towers.

An economic survey estimated that lane closures on the bridge cost around £650,000 (E796,000)/day in terms of user delays, so the temporary bridges, estimated to cost around £6 million ($1 million), make economic sense in the context of a 20-week project.

Dehumidification project The dehumidification project to fight corrosion in the bridge's main suspension cables has made significant progress, despite delays caused by poor weather over the summer.

A report to FETA states that the majority of work on the west cable above the roadway has been completed and work is now progressing on the east cable and the sections underneath the bridge. All of the required power cables and all three dehumidification plants are now in place.

The dehumidification plants will blow very dry air into the cables once they have been wrapped in an airtight neoprene sheath, with the aim of reducing the moisture content within the cables to the point where corrosion cannot occur.

It had originally been expected that the project would result in significant disruption to traffic, but a specially designed access platform that can travel independently up and down the cables meant no lane closures were required.

A 320m trial section of the dehumidification system has been up and running since March this year. The report states that early results are encouraging, but it will not be possible to confirm the overall success of the project until the cables are opened up and re-inspected in 2011/12.

The works were originally due to be finished by October 2009. However, an unusually rainy summer has hindered progress and FETA and contractor are now looking into ways of making up the lost time.

Colford said: "As we all know it's been a particularly wet summer, even by Scottish standards. The whole point of the dehumidification project is to seal the moisture out of the cables, so rain inevitably slows progress.

"Nevertheless, everyone involved has worked incredibly hard and the project has passed some significant milestones. We'll continue to do everything in our power to achieve a successful outcome."

For more information on companies in this article

Related Content

  • Special concrete paver for UK road job
    January 5, 2015
    A specially adapted Wirtgen SP25i concrete slipformer has been used on the M6 motorway near Cannock in the UK. The machine worked together with a Wirtgen ISF25i (independent side feeder) in order to pave a concrete slab under difficult conditions. With an overall length of 373km, the M6 is the longest and one of the most heavily congested motorways in the UK. The M6 connects the M1 motorway near Rugby with Carlisle near the Scottish border. But due to the steadily growing volume of traffic, the Highways
  • Germany to cut red tape for bridge construction up to 2027
    October 5, 2017
    The German federal government has set aside €4.5 billion for refurbishment of 400 bridges in the state of North Rhine-Westphalia up to 2027. Hendrik Wüst, North Rhine-Westphalia transport minister, made the announcement which included around €200 million for road maintenance. The Federal German government also plans to fast-track planning for infrastructure projects. Bonuses to contractors for improved performance to reduce down-time on construction sites as well as the possibily of a six-day working
  • New NY Bridge - Tappan Zee - main span towers poured
    December 16, 2016
    One of the largest US infrastructure projects is nearer completion after recent topping out of the eight main span towers of the New NY Bridge. The final concrete pour was in mid-December and all piles - more than 1,000 - have been installed in Hudson River. To date, 3,000 roadway panels for the approaches - making 5.5km in length - have been installed, according to the New York State Thruway Authority, owner of the New NY Bridge project. The New NY Bridge, also called the Tappan Zee Bridge, is on tra
  • Historic Oakland Bay Bridge receives a new asphalt road surface
    March 31, 2014
    Part of an iconic US bridge has been given a new lease of life, as Mike Woof reports The western section of the historic Oakland Bay Bridge in the US state of California has recently benefited from a series of improvements to strengthen its structural integrity and also upgrade the running surface. Contractor OC Jones & Sons of Berkeley CA, paved large portions of the bridge, taking on two different projects as part of the work. First was placement of the specialised epoxy on the self-anchored suspension (S