Boosting quarry efficiency by cutting fines

The Norwegian quarry firm Feiring Bruk reports an 88% reduction in fines following the commissioning of its new wet processing plant. The firm operates primarily in eastern Norway and has 10 sites extracting and producing crushed stone, gravel and asphalt.
June 4, 2020 Read time: 2 mins
Using a new wash plant is helping boost efficiency for a Norwegian quarry firm

As well as its multiple sites in the east of the country, Feiring Bruk works across Norway for key clients, using mobile crushing and screening plants. Having amassed fines stockpiles at Lørenskog quarry alone, Feiring Bruk was keen to identify a solution that would allow the material to be processed and valuable product recovered.

Modularity and mobility are at the core of equipment designed by CDE and this was an important factor for Feiring Bruk as its operations rely on portability. The firm said that it had a massive amount of material it had been unable to exploit, and which previously would have been deposited. But with the new facility it can now extract washed out particles of zero size and can recover a range of new products the previous system was unable to process.

The washing plant at Feiring Bruk’s Lørenskog quarry comprises an M2500 E5X mobile washing plant with integrated hopper, feed conveyor and P3-75 Infinity Screen and EvoWash sand washing plant. For water processing there is an AquaCycle thickener with automatic dosing station, AquaStore water storage tank and a secure control station. Laboratory tests by Feiring Bruk show that the system washes out 88% of the fines. Before washing, the material contains 65kg of fines per tonne, whereas the washed product has just 8kg of fines/tonne. In fraction 0–20, they have measured 6.5% fines before washing. After washing, the fines content is reduced to 0.75%.

Using its new washing plant, Feiring Bruk is able to make use of a large proportion of the excess product. The wash plant systems are designed to recirculate up to 90% of water, helping to reduce the volume of fresh top-up water required. In addition, the Feiring Bruk plant has been placed on a sloped asphalt surface which allows water to flow into the water basin used as a reservoir.

Products extracted using the new washing plant are attracting the attention of new customers in Norway for their improved grading accuracy. The firm says that its customers want drainage gravel in fraction 8–16 to avoid fines. Now the company can supply drainage gravel in fraction 4–16 that has been washed and is free of fines. The uses for the washed material include asphalt and concrete production and paving stones.

Related Content

  • Asphalt plant innovations coming to market
    April 27, 2015
    A series of new advances in asphalt plant design are now coming to market - Mike Woof writes Key innovations in asphalt plant designs from major manufacturers will offer clients reductions in running costs along with gains in quality control and output. Several of the leading manufacturers are introducing new models that will deliver efficiency gains, as well as options for greater mobility and/or versatility. Swiss-based Ammann is introducing two new mobile plants, the EcoBatch and QuickBatch models,
  • New low emission, versatile asphalt plant from Marini
    January 6, 2017
    Marini’s new eTOWER asphalt plants are said to complete the firm’s Top Tower line-up. The existing Top Tower plants offer capacities of 280-400tonnes/hour and the eTOWER machines are designed with output of 150 and 180tonnes/hour. The units benefits from features used in the Top Tower range such as the drying/filtering tower system. This features as innovative location for the filter and under-filter hopper, above the dryer drum, which is said to help reduce energy consumption. This modular plant can be sup
  • Chinese quarry increasing size of Caterpillar fleet
    December 10, 2013
    Chinese quarry producer Beijing Xindadi Equipment Company is looking to increase the size of its Caterpillar machine fleet as part of its plan to increase output The company is based at Beijing Miyun Taishi Village and currently produces 1-1.5 million tonnes/year of limestone, which is used for general construction in the Beijing area. Zhang Guofeng is equipment manager for the firm and said, “Business is good because the market is not affected by the downturn.”
  • The dark arts of asphalt production
    January 5, 2017
    Asphalt production is a complex process featuring many variables - Mike Varner, chief engineer at Astec Inc discussed methods with Mike Woof Asphalt production in a black art in more ways than one. It involves a complex process of mixing bitumen with aggregates under temperature and optimising this operation is crucial to maximise quality. But with so many variables, determining exactly what is going on inside an asphalt plant involves extensive research, sophisticated computer modelling and the use of a