Pocitelj Bridge reaches banks of Neretva River

Contractors are working to correct a concrete issue on a section of the 100m-long continuous prestressed girder bridge across the Neretva River in Bosnia and Herzegovina.
By David Arminas August 21, 2023 Read time: 2 mins
The Počitelj Bridge, now reaching both banks of the Neretva River, is the largest bridge on the entire pan-European Corridor 5c highway (image courtesy JP Autocesta FbiH – Bosnia and Herzegovina’s motorways agency)

Contractors building the Pocitelj Bridge over the Neretva River in Bosnia are examining damage to a bridge segment that appeared during prestressing of cables.

A crack was discovered on a 4.75m-long segment of deck along the nearly 1km-long structure that rises 100m above the river, according to media reports. Few other details were given.

The bridge is being built by a consortium of Azerbajan construction group Azvirt and Chinese state-owned hydropower engineering and construction companies Sinohydro and Powerchina Roadbridge Group. Hering d.d. Široki Brijeg is a subcontractor and overall construction supervision of the entire Počitelj - Zvirovići motorway is by the Italian group IRD Engineering.

The client, JP Autocesta FbiH – Bosnia and Herzegovina’s motorways agency – has held meeting with the contractors to establish corrective work, the newspaper said. The agency also noted that remedying construction issues at the end of works on such complex structures was normal and all partners are cooperating fully to correct the problem.

In July, the Sarajevo Times reported that work on the final span had been completed allowing connection of the bridge to both banks of the river. Testing and finishing of the decks is now underway for an anticipated opening by the end of the year.

The Počitelj Bridge is the largest bridge on the entire pan-European Corridor 5c highway. The concrete bridge is designed as a continuous prestressed girder bridge with five spans of 147m in length and two connecting side spans of 105m. The box cross-section structure is built by the free cantilever construction method.

Around 38,000m³ concrete, 9,000 tonnes of reinforcement and 1,500 tonnes of prestressing cables were used. Meanwhile, around 20,000m² of asphalt and waterproofing will be installed along the 22m-wide deck in the coming period.

“With the near completion of activities on the Pocitelj – Zvirovici section and the start of construction work on the Prenj tunnel and the Mostar north – Mostar south section and the Kvanj – Buna tunnel, which we plan to contract this year, we are opening new perspectives for the business community and raising the economic potential of this part of Bosnia and Herzegovina (BiH) to a higher level,” said Denis Lasic, acting director of JP Autocesta FbiH.

Related Content

  • Czech bridge sees world formwork debut
    July 23, 2012
    The Czech government is investing heavily in upgrading and modernising the country's top-tier transportation infrastructure. This year alone, building works with a total investment of over E1.6 billion are planned or underway on the Czech motorway and main road network. Completion of the D8 motorway between the Czech capital Prague and Dresden in the east of Germany has a high priority, and as part of this large-scale project, the contracting consortium of SMP and Metrostav is erecting the 585m long Prosmyk
  • ULMA bridges the Danube and Kayak rivers
    March 16, 2021
    The D4 motorway and R7 expressway project is Slovakia’s largest public-private partnership.
  • Work starting on second Chesapeake Tunnel project
    September 20, 2017
    Work is now starting on a major tunnel project in the US state of Virginia. Construction of a second tunnel connection for the Chesapeake Bay is expected to cost US$756million. The original Chesapeake Bay Tunnel and Bridge crossing opened to traffic in April 1964 and measures just over 37km long. Construction of a second parallel bridge was commenced in 1995 and opened to traffic in 1999. However the central tunnel link was not widened at that time and now carries more traffic than it was designed for, whil
  • Polish debut
    July 20, 2012
    PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw