Pocitelj Bridge reaches banks of Neretva River

Contractors are working to correct a concrete issue on a section of the 100m-long continuous prestressed girder bridge across the Neretva River in Bosnia and Herzegovina.
By David Arminas August 21, 2023 Read time: 2 mins
The Počitelj Bridge, now reaching both banks of the Neretva River, is the largest bridge on the entire pan-European Corridor 5c highway (image courtesy JP Autocesta FbiH – Bosnia and Herzegovina’s motorways agency)

Contractors building the Pocitelj Bridge over the Neretva River in Bosnia are examining damage to a bridge segment that appeared during prestressing of cables.

A crack was discovered on a 4.75m-long segment of deck along the nearly 1km-long structure that rises 100m above the river, according to media reports. Few other details were given.

The bridge is being built by a consortium of Azerbajan construction group Azvirt and Chinese state-owned hydropower engineering and construction companies Sinohydro and Powerchina Roadbridge Group. Hering d.d. Široki Brijeg is a subcontractor and overall construction supervision of the entire Počitelj - Zvirovići motorway is by the Italian group IRD Engineering.

The client, JP Autocesta FbiH – Bosnia and Herzegovina’s motorways agency – has held meeting with the contractors to establish corrective work, the newspaper said. The agency also noted that remedying construction issues at the end of works on such complex structures was normal and all partners are cooperating fully to correct the problem.

In July, the Sarajevo Times reported that work on the final span had been completed allowing connection of the bridge to both banks of the river. Testing and finishing of the decks is now underway for an anticipated opening by the end of the year.

The Počitelj Bridge is the largest bridge on the entire pan-European Corridor 5c highway. The concrete bridge is designed as a continuous prestressed girder bridge with five spans of 147m in length and two connecting side spans of 105m. The box cross-section structure is built by the free cantilever construction method.

Around 38,000m³ concrete, 9,000 tonnes of reinforcement and 1,500 tonnes of prestressing cables were used. Meanwhile, around 20,000m² of asphalt and waterproofing will be installed along the 22m-wide deck in the coming period.

“With the near completion of activities on the Pocitelj – Zvirovici section and the start of construction work on the Prenj tunnel and the Mostar north – Mostar south section and the Kvanj – Buna tunnel, which we plan to contract this year, we are opening new perspectives for the business community and raising the economic potential of this part of Bosnia and Herzegovina (BiH) to a higher level,” said Denis Lasic, acting director of JP Autocesta FbiH.

Related Content

  • Major bridge widening project going to plan
    April 11, 2012
    When built it was determined that a vital US road/rail bridge would always be widened. Work on that huge project is going to plan as Patrick Smith reports One of the biggest bridge widening projects in the world is being carried out under an ambitious development programme. At US$1.2 billion, the seven-year scheme to widen the Huey P. Long Bridge in the US state of Louisiana is also the largest of 16 projects planned under the state's TIMED (Transportation Infrastructure Model for Economic Development)
  • Bertha ends her Alaskan Way voyage in Seattle
    December 21, 2017
    Seattle's State Route 99 viaduct is coming down. David Arminas was on site. Bertha, the world’s largest diameter earth pressure balance tunnel boring machine, with a cutterhead diameter of 17.5m, is no more. Her 2.7km journey underneath the waterfront area of Seattle finished on April 4 and the power went off for the last time on an extraordinary TBM that had finally completed an extraordinary job. “A small sidewalk job would have had more impact on city traffic than we have had,” says Brian Russell a v
  • Prenj Tunnel contract to be tendered
    July 4, 2022
    The tunnel in Bosnia will form part of the important European Corridor 5C route.
  • Formwork solutions for bridge maintenance and repair
    January 6, 2015
    An array of innovative formwork solutions have helped in the repair and construction of key bridge links - Mike Woof writes Formwork producers are continually developing novel solutions for bridge maintenance and construction applications. Several key structures have benefited from the novel use of formwork systems, with suppliers such as Doka, PERI, Pilosio and RMD all working on important structures in recent times. In Estonia, construction work is underway on the bypass around Tartu, the country’s