Pocitelj Bridge reaches banks of Neretva River

Contractors are working to correct a concrete issue on a section of the 100m-long continuous prestressed girder bridge across the Neretva River in Bosnia and Herzegovina.
By David Arminas August 21, 2023 Read time: 2 mins
The Počitelj Bridge, now reaching both banks of the Neretva River, is the largest bridge on the entire pan-European Corridor 5c highway (image courtesy JP Autocesta FbiH – Bosnia and Herzegovina’s motorways agency)

Contractors building the Pocitelj Bridge over the Neretva River in Bosnia are examining damage to a bridge segment that appeared during prestressing of cables.

A crack was discovered on a 4.75m-long segment of deck along the nearly 1km-long structure that rises 100m above the river, according to media reports. Few other details were given.

The bridge is being built by a consortium of Azerbajan construction group Azvirt and Chinese state-owned hydropower engineering and construction companies Sinohydro and Powerchina Roadbridge Group. Hering d.d. Široki Brijeg is a subcontractor and overall construction supervision of the entire Počitelj - Zvirovići motorway is by the Italian group IRD Engineering.

The client, JP Autocesta FbiH – Bosnia and Herzegovina’s motorways agency – has held meeting with the contractors to establish corrective work, the newspaper said. The agency also noted that remedying construction issues at the end of works on such complex structures was normal and all partners are cooperating fully to correct the problem.

In July, the Sarajevo Times reported that work on the final span had been completed allowing connection of the bridge to both banks of the river. Testing and finishing of the decks is now underway for an anticipated opening by the end of the year.

The Počitelj Bridge is the largest bridge on the entire pan-European Corridor 5c highway. The concrete bridge is designed as a continuous prestressed girder bridge with five spans of 147m in length and two connecting side spans of 105m. The box cross-section structure is built by the free cantilever construction method.

Around 38,000m³ concrete, 9,000 tonnes of reinforcement and 1,500 tonnes of prestressing cables were used. Meanwhile, around 20,000m² of asphalt and waterproofing will be installed along the 22m-wide deck in the coming period.

“With the near completion of activities on the Pocitelj – Zvirovici section and the start of construction work on the Prenj tunnel and the Mostar north – Mostar south section and the Kvanj – Buna tunnel, which we plan to contract this year, we are opening new perspectives for the business community and raising the economic potential of this part of Bosnia and Herzegovina (BiH) to a higher level,” said Denis Lasic, acting director of JP Autocesta FbiH.

Related Content

  • Bosnia road tunnel project
    December 4, 2020
    A key Bosnian road tunnel project is underway.
  • Korean bridge construction poses challenges
    April 5, 2012
    On South Korea's southern coast, an innovative highway sea crossing is providing many engineering challenges The new Busan-Geoje crosses from South Korea's second city to its biggest island and is slightly shorter than the 12km of the country's famous Incheon project. In addition the main cable stay bridge for the Busan-Geoje project has a 475m span rather than the 800m of the Incheon central span. However the 8.2km Busan-Geoje project faces perhaps greater technical challenges and also includes a second b
  • Korean bridge construction poses challenges
    February 23, 2012
    On South Korea's southern coast, an innovative highway sea crossing is providing many engineering challenges
  • A major highway deal has been awarded by the Bosnian authorities
    May 25, 2012
    Construction work is now going ahead on the Suhodol-Tarcin section of Bosnia’s Corridor Vc highway. The Bosnian Government and highway company Autoceste FBiH Mostar signed a contract with Turkish company Cengiz Insaat Sanayi ve Ticaret for this section of the Corridor Vc highway. The deal is worth €115.2 million and will be for construction of a total of 5km of the motorway. The work is expected to take 28 months to complete. However a consortium of five construction companies from Bosnia and Herzegovina is