Nearly a decade on from when Singapore’s Formula 1 (F1) track was first laid, Shell Bitumen’s high-performance binder, Shell Cariphalte, has been selected once more for resurfacing works. The Federation Internationale de l’Automobile (FIA) sets stringent standards for the performance of its tracks, which are made even more challenging given Singapore’s climate. The road surface must remain constant, despite temperatures of up to 30oC and humidity levels above 70%. The 5km Marina Bay Street Circuit, which
February 22, 2019 Read time: 2 mins
Shell Bitumen’s high-performance binder, Shell Cariphalte is being used at the Singapore F1 race track

Nearly a decade on from when Singapore’s Formula 1 (F1) track was first laid, 763 Shell Bitumen’s high-performance binder, Shell Cariphalte, has been selected once more for resurfacing works.

The Federation Internationale de l’Automobile (FIA) sets stringent standards for the performance of its tracks, which are made even more challenging given Singapore’s climate. The road surface must remain constant, despite temperatures of up to 30oC and humidity levels above 70%.

The 5km Marina Bay Street Circuit, which saw the first ever night-time race back in 2008, must withstand the rigours of everyday traffic as well as the occasional impacts of F1 racing cars travelling at over 300kph and braking around its 23 turns.

Shell Cariphalte was selected for the task because it has been designed to resist extreme heat, rutting, cracking, stripping and ageing. Its tough three-dimensional polymer network gives increased stiffness at high temperatures and low stiffness at low temperatures, increasing the performance range of the pavement and reducing the risk of cracking which is common for surfaces under high stress, says Shell Bitumen.

The resurfacing work, carried out by contractor United E&P, involved laying new asphalt around several of the turn areas. There were also minor changes to Turn 16 and 17, according to motorsport websites, which have been realigned, resulting the in length of the course being reduced by 2m to 5.063km. The work was carried out during the night, when there is less traffic, to minimise disruption.

For more information on companies in this article

Related Content

  • Successful pavement maintenance
    February 16, 2012
    This is the final section of a three-part series about preventive maintenance for pavements. Written by Alan S. Kercher, P.E., Kercher Engineering, Inc
  • Successful pavement maintenance
    April 12, 2012
    This is the final section of a three-part series about preventive maintenance for pavements. Written by Alan S. Kercher, P.E., Kercher Engineering, Inc We practice preventive maintenance in our everyday lives and possibly with agency equipment such as dump trucks and backhoes, but when it comes to maintaining our roadways, most agencies will always defer repairs until the pavements have failed, resulting in very expensive repairs. This article will provide some guidance to help an agency make the switch fr
  • Maputo Airport runway rebuild
    March 26, 2019
    Rebuilding work has been carried out on the runway and taxiways at Maputo International Airport in Mozambique. The work was carried out for Aeroportos de Moçambique, with the engineering handled by NACO and US$64 million of funding being suplied by Agence Française de Dévelopement.
  • Looking around the world with bitumen technology
    March 4, 2015
    Russia needs polymer-modified bitumen; the UK is embracing US-style pavement preservation technology and gearing up to import more bitumen; and Italy prepares to export innovative modifying technology; plus a look at the market in Asia Pacific and the Middle East – Kristina Smith reports. The Total Group has announced two recent deals which underline the changing bitumen market around the world. In Moscow, it is constructing a new type of polymer-modified bitumen (PMB) plant in joint venture with Gazprom Ne