Fort Myer Construction provides paving fit for president Trump

Today, the new US president Donald Trump will be driven triumphantly down Washington D.C.’s famous Pennsylvania Avenue. “The Donald” had a bumpy ride from time to time on his campaign trail to the Oval Office. But the 70-year-old businessman-turned national leader won’t experience any bumps during his historic ride this afternoon, thanks to Fort Myer Construction. Every four years, Fort Myer Construction has the opportunity to provide milling and paving along Pennsylvania Avenue for the District Departme
January 19, 2017 Read time: 3 mins
Fort Myer Construction used a 9.5mm PG70-22 warm mix asphalt
Today, the new US president Donald Trump will be driven triumphantly down Washington D.C.’s famous Pennsylvania Avenue. “The Donald” had a bumpy ride from time to time on his campaign trail to the Oval Office. But the 70-year-old businessman-turned national leader won’t experience any bumps during his historic ride this afternoon, thanks to Fort Myer Construction.

Every four years, Fort Myer Construction has the opportunity to provide milling and paving along Pennsylvania Avenue for the District Department of Transportation to prepare the route for Inauguration Day when the new president is sworn into office.

This past November, Fort Myer Construction tackled the project again.

When not hosting presidential motorcades, Pennsylvania Avenue - often-called America's Main Street – is accommodating countless official parades and processions, as well as protest marches. For normal working people, it is also a major commuter route and is part of the National Highway System.

Fort Myer Construction again had the welcome opportunity to pave the avenue because the company is a subcontractor to Capital Paving which was performing all asphalt operations under the National Highway Systems (NHS) routes contract. This contains a “task order” to resurface Pennsylvania Avenue every four years.
Fort Myer, founded in 1972, is a leading contractor in the Washington D.C. metropolitan area, focusing on an array of infrastructure construction disciplines. The company owns and operates two asphalt plants to supply customers annually with several thousand tonnes of federal- and state-approved mixes.

Importantly, since Fort Myer is the outfit that owns two asphalt plants in the District of Columbia, the company could provide their own asphalt for this job. This was critical to ensure the project remained ahead of schedule and allowed the paving team to reschedule and schedule quick deliveries of asphalt due to weather changes.

Fort Myer’s experience over the years has counted. “We have been either the prime contractor or subcontractor on this contract since 2008,” says Bradley Gardner, general superintendent of the company’s asphalt division.

To begin the Pennsylvania Ave. project, the road was first milled using multiple 2395 Wirtgen W200i milling machines in an echelon fashion, explains Gardner. After milling, brick crosswalks were covered with plastic, then sand was spread on top of the plastic. Curb and gutter were also covered with sand prior to paving. This was done to preserve existing structures along the historical route.

Fort Myer used a 9.5mm PG70-22 warm mix asphalt for paving. “The mix was determined based on the thickness of the lift (nearly 3.2cm) and the temperature during this time of year,” says Gardner. “Only one lift was done to complete this job.”

In total, the project required roughly 5,200tonnes of asphalt and was paved using a 3m 178 Caterpillar AP1055F track paver and two 2.4m track pavers AP655E, AP655F and one 2.4m rubber tyre paver AP600D.

All four pavers were working in echelon formation. The pavement was compacted using 172 BOMAG BW161 rollers for breakdown and a BOMAG BW138 for finish rolling.

The project took six business days to complete - with no weekend work.

For more information on companies in this article

Related Content

  • Fast, cost-effective road stabilisation
    February 15, 2012
    The Kivikko industrial area in Finland, which is owned by the City of Helsinki, has expanded gradually over the years and it has expanded again with the new stabilised area now about 3.5hectares. The ALLU equipment and system was used to stabilise Kivikko for the first time in 2001, and the latest job started in June 2010 with the stabilisation work completed by mid-December 2010. [The ALLU Stabilisation System is a Finnish invention that provides a fast, cost-effective and environmental-friendly working
  • Lafarge picks up Vancouver runway deal
    January 24, 2025
    Lafarge Canada will be a subcontractor to Kiewit and in charge of asphalt paving for Vancouver International’s North Runway project.
  • New northern relief road for Moscow
    August 20, 2015
    New Concession Company to build northern relief road of Moscow Kutuzov Avenue – Eugene Gerden writes New Concession Company has won a tender for the building of the Northern relief road of Kutuzovsky Avenue, a major radial avenue in the Russian capital Moscow. The firm is part of Leader company (one of Russia's largest management companies), owned by Yuri Kovalchuk, a well-known Russian businessman, who is reportedly close to Russia’s president Vladimir Putin. It is planned that the building of the n
  • Iowa expects longer lasting road surface
    June 9, 2015
    In the US state of Iowa, tough paving specifications are resulting in contractors delivering road surfaces that will last longer. The Iowa Department of Transportation (I-DOT) expects to see a highway road surface last 20 years and recently let the contract for a 25.7km road resurfacing project for Highway 92 between Winterset and Greenfield. The 40km link between the two towns sees an average 1,365 cars/day travel on the highway, which was last worked on in 1994 and its surface was due for replacement.