Fort Myer Construction provides paving fit for president Trump

Today, the new US president Donald Trump will be driven triumphantly down Washington D.C.’s famous Pennsylvania Avenue. “The Donald” had a bumpy ride from time to time on his campaign trail to the Oval Office. But the 70-year-old businessman-turned national leader won’t experience any bumps during his historic ride this afternoon, thanks to Fort Myer Construction. Every four years, Fort Myer Construction has the opportunity to provide milling and paving along Pennsylvania Avenue for the District Departme
January 19, 2017 Read time: 3 mins
Fort Myer Construction used a 9.5mm PG70-22 warm mix asphalt
Today, the new US president Donald Trump will be driven triumphantly down Washington D.C.’s famous Pennsylvania Avenue. “The Donald” had a bumpy ride from time to time on his campaign trail to the Oval Office. But the 70-year-old businessman-turned national leader won’t experience any bumps during his historic ride this afternoon, thanks to Fort Myer Construction.

Every four years, Fort Myer Construction has the opportunity to provide milling and paving along Pennsylvania Avenue for the District Department of Transportation to prepare the route for Inauguration Day when the new president is sworn into office.

This past November, Fort Myer Construction tackled the project again.

When not hosting presidential motorcades, Pennsylvania Avenue - often-called America's Main Street – is accommodating countless official parades and processions, as well as protest marches. For normal working people, it is also a major commuter route and is part of the National Highway System.

Fort Myer Construction again had the welcome opportunity to pave the avenue because the company is a subcontractor to Capital Paving which was performing all asphalt operations under the National Highway Systems (NHS) routes contract. This contains a “task order” to resurface Pennsylvania Avenue every four years.
Fort Myer, founded in 1972, is a leading contractor in the Washington D.C. metropolitan area, focusing on an array of infrastructure construction disciplines. The company owns and operates two asphalt plants to supply customers annually with several thousand tonnes of federal- and state-approved mixes.

Importantly, since Fort Myer is the outfit that owns two asphalt plants in the District of Columbia, the company could provide their own asphalt for this job. This was critical to ensure the project remained ahead of schedule and allowed the paving team to reschedule and schedule quick deliveries of asphalt due to weather changes.

Fort Myer’s experience over the years has counted. “We have been either the prime contractor or subcontractor on this contract since 2008,” says Bradley Gardner, general superintendent of the company’s asphalt division.

To begin the Pennsylvania Ave. project, the road was first milled using multiple 2395 Wirtgen W200i milling machines in an echelon fashion, explains Gardner. After milling, brick crosswalks were covered with plastic, then sand was spread on top of the plastic. Curb and gutter were also covered with sand prior to paving. This was done to preserve existing structures along the historical route.

Fort Myer used a 9.5mm PG70-22 warm mix asphalt for paving. “The mix was determined based on the thickness of the lift (nearly 3.2cm) and the temperature during this time of year,” says Gardner. “Only one lift was done to complete this job.”

In total, the project required roughly 5,200tonnes of asphalt and was paved using a 3m 178 Caterpillar AP1055F track paver and two 2.4m track pavers AP655E, AP655F and one 2.4m rubber tyre paver AP600D.

All four pavers were working in echelon formation. The pavement was compacted using 172 BOMAG BW161 rollers for breakdown and a BOMAG BW138 for finish rolling.

The project took six business days to complete - with no weekend work.

For more information on companies in this article

Related Content

  • Trimble’s milling technology wins at Misano World Circuit
    April 4, 2016
    As Europe’s motorcycle racing season gets underway this year, Trimble employees will be avidly following the competitions at one venue in particular – Italy’s Misano World Circuit Marco Simoncelli. A Trimble solution recently helped to efficiently reconstruct the racing surface at Misano, about 14km south-east of the Italian city of Rimini on the eastern Adriatic coast. Since 1991, the racetrack has hosted the World Superbike Championship and, since 2007, the San Marino and Rimini's Coast motorcycle Gran
  • Building the diamond road in Lesotho
    April 6, 2016
    A job site in the Southern African nation of Lesotho represents one of the most extreme and challenging projects to some key Italian firms of the last 10 years. The project was certainly different from the norm It involves building a road in the Lesotho Mountains, some 200km from the capital Maseru, with the work being carried out by the Cooperative of Building and Cement workers from Ravenna (CMC). CMC, which has ranked among Marini's clients for many years now, is involved in the construction of a
  • FAYAT buying majority stake in ADM
    July 3, 2024
    FAYAT is buying a majority stake in US firm ADM.
  • Pavers providing smooth runway for Saudi Arabia
    October 2, 2014
    Jeddah’s international airport in Saudi Arabia is benefiting from a major revamp to help boost capacity. The King Abdulaziz International Airport (KAIA) near Jeddah has seen a massive increase in passenger numbers in the last 20 years Demand has continued to grow due to both business travel and religious tourism and the KAIA authorities opted to expand the facilities in 2006, in line with anticipated needs. That first phase of the planned expansion is being completed during this year, making KAIA the la