Call for rising bitumen cost to be factored into highways contracts

Rising bitumen prices should be factored in more consistently when awarding highways contract tenders, according to Tarmac National Constructing (TNC). The near 60% bitumen price hike of the last two years, driven by a major decrease in European refinery production, is said by TNC to be making it “extremely difficult” for highways contractors to tender for work, as current price fluctuation mechanisms do not fairly compensate for significant extra input costs. TNC says that while the Highways Agency’s
April 20, 2012 Read time: 2 mins
Rising bitumen prices should be factored in more consistently when awarding highways contract tenders, according to 2399 Tarmac National Constructing (TNC).

The near 60% bitumen price hike of the last two years, driven by a major decrease in European refinery production, is said by TNC to be making it “extremely difficult” for highways contractors to tender for work, as current price fluctuation mechanisms do not fairly compensate for significant extra input costs.

TNC says that while the 2309 Highways Agency’s Category Management Contracts and a minority of council tenders use appropriate price fluctuation mechanisms, they are not being consistently applied across all national network and local authority road contracts.

The leading UK road maintenance and highways services company says it is turning to alternative road construction methods with bitumen, which accounts for around a third of the cost of constructing a new road, being replaced with composite road construction on new build schemes.

Paul Fleetham, managing director of TNC and Middle East, said:

“With one of the largest UK refiners, 741 Petroplus, entering administration last month, the general trend is for less bitumen to be available, exerting additional cost pressures.

“The industry is at a tipping point as it tries to recover these exceptional increases on existing contracts and anticipate the negative impact these may have when tendering for future long-term highway works.”

For more information on companies in this article

Related Content

  • Reduced emissions, costs, with recycled asphalt
    February 21, 2012
    Recycling is a key issue for asphalt road construction, with many technologies now coming to market. Bith an ever increasing emphasis on sustainability forcing change in the construction sector in Europe and North America, the highway sector now has to seek new solutions.
  • “Bold and brave” rallying call to cash-starved UK highway maintenance teams
    July 24, 2012
    UK local authorities and other organisations must be “bold and brave” in their structuring of repair and maintenance works, delegates at a key road engineering conference in Birmingham, central England were told. Speaking at the Developments in Pavement Assessment (DIPA 2012) event Les Hawker, highways manager at Transport for London (TfL), said: “There is no extra money and only 20% of the [Government budget] cuts have taken place so far. Over the next five years the other 80% of cuts will come through. Or
  • The radically changing face of UK highways management
    May 14, 2014
    The British Government policy paper ‘Action for Roads: A network for the 21st century’ sets out radical change to the strategic way roads are funded and managed – including plans to turn the Highways Agency into a Government-owned company and a pledge to invest over €33.4 billion (£28 billion) in roads maintenance between 2015 and 2020. Jenny Moten, Highways Agency divisional director for Network Services, gave a keynote presentation on the new approach to strategic highways management during the Road Safet
  • Bitumen provides more durable road surface
    February 7, 2012
    When the main commuter route into Cardiff, the Welsh capital, began to suffer from acute deformation, the Vale of Glamorgan Council required a durable and faster alternative to hot rolled asphalt to ensure minimum disruption for local road users.