Call for rising bitumen cost to be factored into highways contracts

Rising bitumen prices should be factored in more consistently when awarding highways contract tenders, according to Tarmac National Constructing (TNC). The near 60% bitumen price hike of the last two years, driven by a major decrease in European refinery production, is said by TNC to be making it “extremely difficult” for highways contractors to tender for work, as current price fluctuation mechanisms do not fairly compensate for significant extra input costs. TNC says that while the Highways Agency’s
April 20, 2012 Read time: 2 mins
Rising bitumen prices should be factored in more consistently when awarding highways contract tenders, according to 2399 Tarmac National Constructing (TNC).

The near 60% bitumen price hike of the last two years, driven by a major decrease in European refinery production, is said by TNC to be making it “extremely difficult” for highways contractors to tender for work, as current price fluctuation mechanisms do not fairly compensate for significant extra input costs.

TNC says that while the 2309 Highways Agency’s Category Management Contracts and a minority of council tenders use appropriate price fluctuation mechanisms, they are not being consistently applied across all national network and local authority road contracts.

The leading UK road maintenance and highways services company says it is turning to alternative road construction methods with bitumen, which accounts for around a third of the cost of constructing a new road, being replaced with composite road construction on new build schemes.

Paul Fleetham, managing director of TNC and Middle East, said:

“With one of the largest UK refiners, 741 Petroplus, entering administration last month, the general trend is for less bitumen to be available, exerting additional cost pressures.

“The industry is at a tipping point as it tries to recover these exceptional increases on existing contracts and anticipate the negative impact these may have when tendering for future long-term highway works.”

For more information on companies in this article

Related Content

  • German construction equipment industry’s sales rise 8 per cent
    February 18, 2015
    German manufacturers of construction equipment reported an 8% rise in sales, amounting to €8.4 billion. The level was higher than expected and equal to sales in 2006, according to the Construction Equipment and Building Material Machinery Association (VDMA). However, the VDMA, part of the German Engineering Federation, suggested that company profits may not have risen along with sales and tough times remain ahead. “Turnover is one thing, profit is another,” Joachim Strobel, deputy chairman of VDMA, said.
  • Tarmac’s productivity boost with new software
    August 9, 2018
    A highly sophisticated software system is at the heart of a major boost to productivity and efficiency from contractor Tarmac. The firm is utilising the latest logistics software from Germany to improve its performance. The company is the first contractor in the UK to employ the BPO ASPHALT software developed by Volz Consulting in Germany. This advanced planning and real-time software technology can be utilised to optimise road construction logistics and boost productivity. The software allows Tarmac’s co
  • Caterpillar's new buckets
    February 17, 2012
    Caterpillar Work Tools is introducing a new line of pin-on and coupler buckets for its 374D and 390D hydraulic excavators, featuring improved designs to take advantage of increased machine performance.
  • Caterpillar's new buckets
    April 5, 2012
    Caterpillar Work Tools is introducing a new line of pin-on and coupler buckets for its 374D and 390D hydraulic excavators, featuring improved designs to take advantage of increased machine performance.