Call for rising bitumen cost to be factored into highways contracts

Rising bitumen prices should be factored in more consistently when awarding highways contract tenders, according to Tarmac National Constructing (TNC). The near 60% bitumen price hike of the last two years, driven by a major decrease in European refinery production, is said by TNC to be making it “extremely difficult” for highways contractors to tender for work, as current price fluctuation mechanisms do not fairly compensate for significant extra input costs. TNC says that while the Highways Agency’s
April 20, 2012 Read time: 2 mins
Rising bitumen prices should be factored in more consistently when awarding highways contract tenders, according to 2399 Tarmac National Constructing (TNC).

The near 60% bitumen price hike of the last two years, driven by a major decrease in European refinery production, is said by TNC to be making it “extremely difficult” for highways contractors to tender for work, as current price fluctuation mechanisms do not fairly compensate for significant extra input costs.

TNC says that while the 2309 Highways Agency’s Category Management Contracts and a minority of council tenders use appropriate price fluctuation mechanisms, they are not being consistently applied across all national network and local authority road contracts.

The leading UK road maintenance and highways services company says it is turning to alternative road construction methods with bitumen, which accounts for around a third of the cost of constructing a new road, being replaced with composite road construction on new build schemes.

Paul Fleetham, managing director of TNC and Middle East, said:

“With one of the largest UK refiners, 741 Petroplus, entering administration last month, the general trend is for less bitumen to be available, exerting additional cost pressures.

“The industry is at a tipping point as it tries to recover these exceptional increases on existing contracts and anticipate the negative impact these may have when tendering for future long-term highway works.”

For more information on companies in this article

Related Content

  • Road markings important for road safety
    February 20, 2012
    Manufacturers are constantly upgrading marking materials and equipment. Now those responsible for highways are being asked to do more as Patrick Smith reports. A recent report claimed that nearly one-third of the length of Britain's single carriageway A-roads have white lines so worn out that they do not meet recognised standards. According to the LifeLines Report, an assessment of more than 2,400km of the road network, Britain's most dangerous roads have the most worn-out centre line markings of all, leavi
  • A new event is preparing the asphalt industry for tomorrow’s world
    September 11, 2018
    An inaugural event for the European bitumen industry urged attendees to look to the future - Kristina Smith reports What will tomorrow’s roads look like? Will lanes be narrower, will the road charge vehicles as they drive on them, will they collect data, will they be self-cleaning and de-polluting? All these questions and more were pondered at a two-day conference in Berlin, entitled ‘Preparing the asphalt industry for the future’. It was the first such event for Eurasphalt & Eurobitume (E&E), and set a
  • The cycle of potholes in the UK
    October 1, 2019
    Since 2015 almost a million potholes have been recorded annually by UK local authorities, with the 2016 count reaching 1,088,965, according to an insurance provider.
  • The new agile world of the construction equipment industry
    June 22, 2015
    while worldwide for 2015 a crystalball would be helpful, in Europe the sector has already listed specific priorities it wants to tackle, and among these are the upcoming emissions regulations (see separate story), external trade and access to foreign markets, and market surveillance.