Call for rising bitumen cost to be factored into highways contracts

Rising bitumen prices should be factored in more consistently when awarding highways contract tenders, according to Tarmac National Constructing (TNC). The near 60% bitumen price hike of the last two years, driven by a major decrease in European refinery production, is said by TNC to be making it “extremely difficult” for highways contractors to tender for work, as current price fluctuation mechanisms do not fairly compensate for significant extra input costs. TNC says that while the Highways Agency’s
April 20, 2012 Read time: 2 mins
Rising bitumen prices should be factored in more consistently when awarding highways contract tenders, according to 2399 Tarmac National Constructing (TNC).

The near 60% bitumen price hike of the last two years, driven by a major decrease in European refinery production, is said by TNC to be making it “extremely difficult” for highways contractors to tender for work, as current price fluctuation mechanisms do not fairly compensate for significant extra input costs.

TNC says that while the 2309 Highways Agency’s Category Management Contracts and a minority of council tenders use appropriate price fluctuation mechanisms, they are not being consistently applied across all national network and local authority road contracts.

The leading UK road maintenance and highways services company says it is turning to alternative road construction methods with bitumen, which accounts for around a third of the cost of constructing a new road, being replaced with composite road construction on new build schemes.

Paul Fleetham, managing director of TNC and Middle East, said:

“With one of the largest UK refiners, 741 Petroplus, entering administration last month, the general trend is for less bitumen to be available, exerting additional cost pressures.

“The industry is at a tipping point as it tries to recover these exceptional increases on existing contracts and anticipate the negative impact these may have when tendering for future long-term highway works.”

For more information on companies in this article

Related Content

  • Looking around the world with bitumen technology
    March 4, 2015
    Russia needs polymer-modified bitumen; the UK is embracing US-style pavement preservation technology and gearing up to import more bitumen; and Italy prepares to export innovative modifying technology; plus a look at the market in Asia Pacific and the Middle East – Kristina Smith reports. The Total Group has announced two recent deals which underline the changing bitumen market around the world. In Moscow, it is constructing a new type of polymer-modified bitumen (PMB) plant in joint venture with Gazprom Ne
  • Sea-changes ahead for bitumen pricing
    May 16, 2020
    Both pricing and – importantly – supply patterns will change.
  • The bitumen market is changing globally and products is being transported further
    August 21, 2014
    Political and economic changes around the world are impacting on the way bitumen is supplied and used - Kristina Smith reports on the Argus Europe Bitumen conference in Rome, and highlights some of the new technologies being launched to address these changes Attendees at the Argus Europe Bitumen Conference, held in Rome on 11th and 12th June heard how the global bitumen market is changing. More refineries are expected to close in Europe; the US, with its shale oil, is dominating bitumen supply to some re
  • M25 maintenance contract for Tarmac in UK
    May 25, 2017
    Contractor Tarmac has won a deal that will see the firm carrying out maintenance work on the UK’s M25 motorway. The contract is worth some £10 million/year and is for M25 operator and maintenance company, Connect Plus. The M25 motorway is one of the busiest road links in Europe and runs around UK capital London. The agreement will be for a period of up to 12 years and will see Tarmac carrying out resurfacing work for a total of 440km of motorway as well as the key link roads around London. Tarmac will also