Wirtgen’s 3800 CR rips it up in San Jose

In California, in-situ cold recycling with a Wirtgen 3800 CR recycler has proved to be the most economical solution. In the US’s Golden State – California – Wirtgen’s 708kW powerhouse the 3800 CR recycler resurfaced 160km of San José’s main traffic arteries in situ, on-the-spot. The 3800 CR worked with a Vögele VISION 5200-2i tracked paver in a rear-load process. With this method, the 3800 CR travels in reverse, removing the damaged asphalt layers in a down-cut process and transferring the recycled material
May 16, 2017 Read time: 3 mins
In situ in California: Wirtgen’s Recycler 3800 CR
In California, in-situ cold recycling with a Wirtgen 3800 CR recycler has proved to be the most economical solution


In the US’s Golden State – California – 2395 Wirtgen’s 708kW powerhouse the 3800 CR recycler resurfaced 160km of San José’s main traffic arteries in situ, on-the-spot.

The 3800 CR worked with a 1194 Vögele VISION 5200-2i tracked paver in a rear-load process. With this method, the 3800 CR travels in reverse, removing the damaged asphalt layers in a down-cut process and transferring the recycled material to the paver.

The contractor, MCK Services, elected to use the process for this job to achieve a particularly high level of paving quality. In the down-cut process developed by Wirtgen, the milling drum rotates in the direction of travel, not against it as in the up-cut process. As a result, particle size can be precisely controlled when processing the material, especially on very brittle, thin, old asphalt roads.

One illustrative example is W. Campbell Avenue, a main road in San José in the heart of Silicon Valley. The Wirtgen cold recycler first milled off a 10.2cm layer of damaged asphalt across a width of nearly 3.9m, granulated it and mixed in the 1% pre-spread cement.

Two tank trucks supplied the recycler with hot bitumen and water via connected hose lines. Added pressurized air generates foamed bitumen. Microprocessor-controlled injection bars ensure precision injection of the foamed bitumen – in this case 2.5% – into the mixing chamber, where it is optimally processed with the granulated material. Ejectors positioned on the rotor then transfer the mix to the 3800 CR’s conveyor belt.

Meanwhile, traffic in front of the Starbright Theater, at the corner of Fulton Street, continued to flow by the recycling train, thanks to the fact that pavement rehabilitation is completed in a single pass. There were no trucks having to weave in and out of the lane. This increases safety and is a tremendous relief to the traffic system.


Wirtgen’s 3800 CR machine concept is geared to maximum output so that rehabilitation projects can be completed quickly. With this in mind, the conveyor system has an extremely high conveying capacity. The slewing and height-adjustable conveyor rapidly transfers material to the material hopper on the tracked paver, which then places a 10.2cm layer and pre-compacts the surface. The HD+ 110 VVHF tandem roller and GRW 280i pneumatic tyre roller from 228 Hamm perform final compaction, giving the road a closed, smooth surface texture.

“Thanks to the Wirtgen 3800 CR, we were able to fully comply with the traffic and budget requirements stipulated by the City of San José,” said Bob Garrigan, superintendent at MCK Services.

Around 9,600 fewer truck hours significantly reduced CO2 emissions, fuel consumption and construction traffic on streets that receive between 12,000 and 35,000 vehicles daily. In total, the city saved about US$1.5 million. Frank Farshidi, project manager for the city, said that cold recycling in-situ proved itself to be “extremely economical, environmentally-friendly and has the least impact on the public”.

For more information on companies in this article

Related Content

  • Vögele MT 3000-2 for Austria A2 motorway
    May 14, 2014
    Road construction work with moving traffic always represents a major challenge. This is especially true when only one lane can be closed, consequently leaving little space for working and manoeuvring. That was exactly the case for a rehabilitation project on the A2 motorway in Austria between Vienna and Graz near Schäffern. However, the job was further complicated by another factor: all access roads to the job site were roughly 1km apart. Ensuring an uninterrupted supply of mix to the paver under these
  • Rebuilding a scenic route in South Africa
    April 20, 2018
    Equipment from Wirtgen has played a key role in the rehabilitation of a major route in Cape Town. The scenic Camps Bay Drive provides access to Camps Bay and Hout Bay Based on the project brief and geometric analysis, Camps Bay Drive required widening to cope with high volumes of tourist traffic and MyCiti buses. In order to minimise the impact on traffic, the design brief targeted construction outside the summer peak tourist season and also required investigation into shortened construction periods. The
  • Road recycling saves time and costs, reduces emissions
    February 13, 2012
    Stabilisers bring recycling improvements to roads in the UK and Armenia. The local road authorities near the UK city of Bath have saved nearly €250,500 on the cost of repairing a 400m long section of the B3110 Midford Road. This saving has been achieved by opting to recycle and strengthen in-situ the existing surface, instead of using conventional full depth pavement reconstruction.
  • Efficient recycling and soil stabilisation from Wirtgen 
    October 26, 2022
    Wirtgen says that its latest WR recyclers/stabilisers are more efficient due to the development of the new Resource Efficiency System (RES). This increases the degree of automation in the overall process, boosting efficiency.