Skip to main content

Russian quarry increases efficiency with Sandvik equipment

A quarry facility in Russia has increased working efficiency by using Sandvik machinery. Located in in the Kurgan Region (Urals) of Russia, the Sinarsky Quarry is benefiting from an increase in throughput and reduced downtime since its new Sandvik crushing and screening plant became fully operational. The company invested over €2 million on the new plant, and is aiming to use it in order to double its aggregates production. This increase in production is required in order to meet the doubling of demand for
August 20, 2015 Read time: 3 mins
The new Sandvik crushing and screening equipment is helping the Sinarsky Quarry in Russia achieve its planned doubling of capacity
A quarry facility in Russia has increased working efficiency by using Sandvik machinery

Located in in the Kurgan Region (Urals) of Russia, the Sinarsky Quarry is benefiting from an increase in throughput and reduced downtime since its new 325 Sandvik crushing and screening plant became fully operational. The company invested over €2 million on the new plant, and is aiming to use it in order to double its aggregates production. This increase in production is required in order to meet the doubling of demand for aggregates to be used on local authority road construction and infrastructure development projects.

The aggregates from the Sinarsky Quarry are in high demand as they offer high resistance and density, which is due to the geological qualities of the local touchstone and liparite. However, these attributes come at a price. The rock is very demanding on the efficiency of crushing and screening equipment.

When the management of the quarry sought to improve production it was decided to source equipment from a reliable European supplier that would be able to provide a suitable solution and deliver the increased demand for materials. To this end the firm contacted Sandvik Construction in Russia, which was able to supply the equipment and develop a suitable crushing and screening process that maximises output while ensuring accurately sized products.

Following discussions between Sandvik and quarry management it was agreed that the best solution for improving production was to supply an assortment of stationary equipment, comprising of three crushers, two screens, three feeders and one grizzly feeder. The first stage of the process sees the rock being fed to a ST1263 grizzly feeder. Here around 9% of fines (0–20mm) are separated.  The material then proceeds to a CJ411 jaw crusher for primary crushing.

Following this the secondary crushing is performed by a CH440 cone crusher with an EC chamber which produces 0–5, 20-40 and 40–70mm fractions. After screening by a CS108, the oversize material is then recycled. The 5–20mm, 20–40mm and 40–70mm fractions are then fed into a CH440 cone crusher with an F-chamber for tertiary crushing.

The quarry was initially aiming to produce 5–20mm aggregates with 10% flakiness, but the first laboratory tests showed that the flakiness index to be below 5%. After tertiary crushing the material is fed into a CS126 triple deck screen which produces 0–5mm and 5–20mm final fractions. At first the share of the 5–20mm fraction was 36%, but thanks to the flexibility of the new plant, the quarry is now able to automatically change the volume ratio of desired fractions and thereby anticipate fluctuations in market demand.  

In order to ensure that production requirements are being met a six-month trial period was scheduled. During this time the operators will undertake any required upgrades and find the best parameters for more efficient crushing.

However, the management of the Sinarsky Quarry foresees just a few shutdowns being required, as all the constituent crushing and screening parts have been primarily selected and configured in accordance with the results of geological tests performed by Sandvik specialists. This means that the equipment is focused on providing the best possible performance under the exacting current quarrying conditions.

The Sinarsky Quarry operation is proving to be a great success. This is not the only plant that Sandvik Construction has installed. However, it is the first of its kind.

For more information on companies in this article

Related Content

  • Increasing quarry production efficiency in the UAE
    June 7, 2016
    UAE company National Quarries has managed to increase crushing efficiency following the commissioning of new plant. The firm’s existing crushing plant was doing satisfactory work, but the company’s management felt performance was lacking. As a result, the company approached Sandvik Construction Middle East, which offered the modern solution of using a CH660 cone crusher. The new unit has delivered improved production leading to even more orders for Sandvik equipment. In order to produce the large amount
  • Nigerian asphalt producer increasing capacity with Sandvik plant
    June 30, 2014
    In Nigeria a major asphalt producer is increasing production capacity to cope with growing demand for its materials Nigeria is developing its road and highway network, which has triggered greater demand for quality aggregates and asphalt for construction. Producer Asphalt Unity Construction is now meeting this demand with its purchase of new mobile equipment from Sandvik Construction.
  • Sila's Sandvik Thai success
    July 17, 2012
    The Sila Sanon limestone quarry in Thailand is playing a key role in providing high quality aggregates for the growing Thai construction industry.Recently the family-owned operation has invested in a full range of crushing and screening plant supplied by Sandvik Construction’s dealer in Thailand, the William Wong Group, and the quarry is now able to supply over 200,000tonnes of accurately sized materials on a monthly basis. The Sila Sanon Quarry in Saraburi Province, just over 100km north of the capital Ba
  • New aggregate plant for Sinoma Cement in China
    May 16, 2016
    Sinoma Cement is one of the largest cement manufacturers in the Peoples Republic of China. In 2012 the company decided to boost its aggregate production, both for its own use in cement production, and to supply aggregates to the local construction market. In order to do this Sinoma Cement invested in two aggregate plants supplied by Sandvik Construction, consisting of feeders, screens, jaw and impact crushers. The firm’s extensive production of clinker cement is facilitated through three production lines