Asphalt plans silos increase efficiency, reduce waste

A Colombian contractor tackles specifications for asphalt road work with Astec equipment.Award-winning Colombian contractor MHC has upgraded its Astec Portable Double Barrel plant to handle highway and other projects. The plant, installed in Bucaramanga, equipped with two RAP [recycled asphalt pavement] bins, a Double Barrel Green System, and one New Generation silo was bought by MHC in 2009. It has now received a second silo and a truck scale extension.
April 10, 2012 Read time: 4 mins
MHC's Portable Double Barrel plant installed in Bucaramanga, Colombia

A Colombian contractor tackles specifications for asphalt road work with Astec equipment

Award-winning Colombian contractor MHC has upgraded its 1250 Astec Portable Double Barrel plant to handle highway and other projects.

The plant, installed in Bucaramanga, equipped with two RAP [recycled asphalt pavement] bins, a Double Barrel Green System, and one New Generation silo was bought by MHC in 2009. It has now received a second silo and a truck scale extension.

MHC is a USO 9001:2000 corporation presided over by Mario Huertas Cotes, and is a leading road contractor with headquarters in Colombia’s capital Bogota.

Established in 1975, it specialises in engineering and mining as well as dams, bridges, and heavy road construction using asphalt. On some of these roads MHC has remained as a concessionary partner with all maintenance operations.

In 1994, the company obtained the coveted National Engineering Prize for the Sesquile Dam, and it currently has two contracts with 2812 Invias (National Highway Institute).

One contract involves the rehabilitation and maintenance of roads located in Montería in the Department of Córdoba with a mix use of 15,000tonnes per month at an elevation of 305m above sea level.

One of the issues relating to the contract was the procurement of aggregates, which led the contractor to use limestone with “great results.”

The second contract was for the study, design, land use, social, environmental, and construction aspects of a 205km long, four-lane highway between Bucaramanga and Cúcuta in the Department of 4001 Santander.

The main issue with this project was obtaining the land to install the asphalt plant and crushing equipment. The end result was installing the Astec equipment in the limestone quarry at Surata outside the city of Bucaramanga.

According to president Mario Huertas, the Astec plant was the best solution to guarantee a permanent and ready supply of hot mix while meeting the contractor's specifications.

 “The delivered product is very homogenous and the plant is well below the local environmental gas emissions standards and calories (heat) emissions to the atmosphere,” he explained.

“The 95% uptime and safety features of the plant have greatly contributed to an overall cost reduction in production.”

He also noted the reduction in the cost of consumables, burner fuel and a reduction in the oxidation of the daily mix production.
Huertas praised the innovation of the Astec equipment when it came to the Double Barrel Green System and New Generation storage silos.

“The Green System added to the Double Barrel drum mixer allows me to reduce fuel consumption and increase production. The warm mix asphalt does not need the addition of expensive commercial additives: using water with the mix along with the liquid asphalt cement is all that is needed.

“We are able to store mix in the Astec New Generation HMA [hot mix asphalt] storage silo for four days without the loss of mix quality.”

By keeping the silo full, the plant is always ready to meet customer demand; equipment efficiency is maximised and material waste is reduced.

In storage mode, the silos are completely sealed at the top and the bottom to prevent oxidation.

“I have become convinced that silos allow you to increase daily production with a substantial reduction in operational costs for the mix made on the previous day, which allows a better and more efficient use of human resources to mix transport trucks to feed the road works,” said Huertas.”

To date, MHC has three 2987 Telsmith aggregate classifiers (Model 2561T); two impact crushers (Model FT4240); one vertical axis impact crusher 2500; one Astec Mobile Screens model PTSC (Model 3618Vm), and one ProSizer (Model 2612V).

“The relationship with Astec is a partnership that goes beyond basic customer service,” acclaimed Huertas.

“The Astec Group knows its products; knows how to relate the technologies to my applications, and knows how to provide excellence in customer service. This is evident through all Astec divisions and the people that represent the company, including our Colombia Astec agent, Rodriguez and Londono.”

Meeting the standards required by MHC's customers is not a problem, according to Huertas, who said Astec listened to his technical and business suggestions, thus allowing him to purchase equipment to provide better production, a reduced maintenance cost, and a better mix quality to his operations.

“In terms of service, Astec has been very effective, receptive, timely, and very experienced. With the conditions in Colombia, we need a good response on parts for routine maintenance.

“Astec has maintained the added value with its customers through its post-sale relationship between local agents and end customers.”

For more information on companies in this article

Related Content

  • Advancing asphalt plant technology
    June 9, 2016
    Advances in asphalt plant technology were in major evidence at the bauma 2016 exhibition in Munich - Mike Woof writes One of the most apparent developments at bauma 2016 was the strong focus on asphalt plant technology. The massive physical presence of the asphalt plants could be seen from a distance, right across the showground, particularly the 50m-high machine Benninghoven had opted to exhibit. However, other plant systems from rival firms Ammann, Lintec and Marini, as well as Turkish company E-MAK, c
  • Astec Industries CEO and president Ben Brock says stay focused and true to win
    July 8, 2016
    Core values, constant innovation and looking after the customer are the key drivers for Ben Brock, chief executive officer and president of Astec Industries. How does he keep his company ahead of the pack and what does he think that the future holds? if you ask Ben Brock to explain how his Astec Industries group has managed to do so well for so long, he doesn’t even pause for breath. “That’s easy, I thank the good doctor. He always told me: do good work and take care of the customer ... which is exactl
  • The dark arts of asphalt production
    January 5, 2017
    Asphalt production is a complex process featuring many variables - Mike Varner, chief engineer at Astec Inc discussed methods with Mike Woof Asphalt production in a black art in more ways than one. It involves a complex process of mixing bitumen with aggregates under temperature and optimising this operation is crucial to maximise quality. But with so many variables, determining exactly what is going on inside an asphalt plant involves extensive research, sophisticated computer modelling and the use of a
  • Asphalt plant operators offer fuel for thought
    August 28, 2013
    Asphalt plant operators across continental Europe are said to be increasingly turning to pulverized lignite to fuel or partially fuel production, while leading plant manufacturers have been busy closing key deals with customers in Russia, Bangladesh and Switzerland. Guy Woodford reports. Financially astute asphalt plant operators in Europe are said to be increasingly using pulverized lignite, also known as brown coal, from Germany to fuel or partially fuel production. Under the product name ‘Lignite Energ