Stable site

A Wirtgen soil stabilisation machine has been treating a 100,000m2 site in Staffordshire for an advanced logistics centre, a project including access roads and parking areas. The WR2500S recycler is being used to prepare the way for the vast Blue Planet complex in Chatterley Valley, Newcastle-under-Lyme. Throughout the preliminary groundworks the Wirtgen machine, purchased by Barton Plant of Kettering, Northamptonshire, has placed between 6-7,000m2/day of lime/cement stabilised earth on the project, for mai
July 23, 2012 Read time: 2 mins
A 2395 Wirtgen soil stabilisation machine has been treating a 100,000m2 site in Staffordshire for an advanced logistics centre, a project including access roads and parking areas. The WR2500S recycler is being used to prepare the way for the vast Blue Planet complex in Chatterley Valley, Newcastle-under-Lyme. Throughout the preliminary groundworks the Wirtgen machine, purchased by Barton Plant of Kettering, Northamptonshire, has placed between 6-7,000m2/day of lime/cement stabilised earth on the project, for main contractor McLaren Construction. The WR2500S was also joined on site by two new Streumaster spreaders, also supplied by Wirtgen.

Barton began the works by stripping off 12,000m3 of topsoil, which was followed by a 25,000m3 cut-to-fill earthworks operation. The Wirtgen has been used to lay a 300mm thick cement/lime treated layer and externally this rises to 400mm thickness, while in the car park areas it is 250mm. These areas are trimmed variously to a sub-base tolerance of +10 to -30mm, or +10 to -20mm.

Barton owns an extensive earthmoving fleet and has invested in the new machines to meet the needs of the fast-growing ground stabilisation sector. With its 500kW rated 2796 Mercedes Benz V12 engine, the WR2500S has plenty of power for soil stabilisation as well as for pulverising or cold recycling. All-wheel-drive and hydraulic height adjustable wheels allow the WR2500S to handle difficult terrain while the four-wheel steering system allows an operator to choose between normal, crab-steer, or coordinated steering modes for use in cramped sites.

For more information on companies in this article

Related Content

  • Highway project in Texas required demolition equipment
    May 1, 2018
    A contractor in Texas has used equipment from Brokk to help out with a tricky highway project. Upgrading work has been carried out on a 6.4km-long stretch of I-35 in San Antonio between Loop 410 NE and Loop 410 S. This stretch of the route was carrying around 185,000 vehicles/day and was suffering increasing levels of congestion at peak periods. Travel times lengthened by 65% during rush hour, while ramps on opposite sides of the interstate caused additional congestion and safety issues. In one section, t
  • Advances in bitumen technology: new applications
    February 16, 2022
    This month, we look at four very different pavement technologies in four very different applications
  • Italian stabilization efficiency from FAE
    March 18, 2016
    Italian firm FAE continues to develop its recycling technology, now offering two stabiliser packages for large and small operations. The smaller SSM and SSM/HP units operate with working depths down to 400mm. Meanwhile the larger SSH unit has a working width of 2.5m, suits towing machines with power outputs from 120-300kW, and can handle working depths down to 500mm. A key development is the firm’s innovative automatic injection system (AIS), which now offers a more efficient and effective mixing of wate
  • Mexico’s new Jala-Puerto Vallarta Highway
    August 29, 2017
    Mexico’s highway infrastructure plays a key role in the country’s economy, carrying around 55% of its freight and 98% of its passenger traffic. To meet this demand, the network has 377,660km of roads in all. This is split between the 49,652km federal highway network, the 83,982km of state roads, 169.429km of rural roads and 74,596km of access roads. mHowever, although the federal road network manages to connect a large part of the country's strategic points, some stretches already present problems with satu