The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany.
February 29, 2012 Read time: 3 mins
The BOMAG milling machines worked reliably within a tight time frame
The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany. Upgrade work to the B50 Bundestrasse that connects with the airport is of prime importance and contractor Beitz-Fräsdienstleistungen is widening a 7.5km section of the road. The work will see the road widened and upgraded from two lanes to four-lane and this has been speeded by the high productivity of 172 Bomag planing equipment.

The work was carried out in three different stages with the first stage being planing to a depth of 40mm over a length of 7.5km, an area of 50,000m2. This work removed around 4,500tonnes of material and 180 truck loads were required to haul the milled cuttings away. The second stage was the milling of another 4,500m2 of surface to improve weak points in the road structure, which removed 1,350tonnes of binder and base layers and required a further 55 truck loads to haul the material away. The third and final stage of the milling job was to remove a 150m stretch of 6m wide binder and base layers to a depth of 320mm in front of bridges and this required the removal of 700tonnes of material in a further 28 trucks. In all the milling work required some 6,550tonnes of material to be removed.

The work had to be finished within a tight time frame and the BOMAG BM 2000/60 cold planers worked reliably and productively within the schedule. The planing work had to be completed within a single week during the day from 06.30-17.00 and with a public holiday on the Thursday, the time frame was tighter still. In spite of the surface layer being hard and only a few years old, an average milling speed of 25 m/min was achieved over the 7.5km during the first stage of the planing work. This gave a perfect, clean planed surface that allowed for quick, precise re-laying of the new surface and reduced the time needed for sweeping the road afterwards. During all three stages the average fuel consumption was an encouraging 60-65litres/hour, while cutter wear was minimised due to the effective water spraying system for the planer. Productivity was further boosted by the automatic settings that returned the cutting depth to the same height when each truck carrying the milled material was moved into place under the discharge conveyor.

For more information on companies in this article

Related Content

  • Drilling efficiency
    April 13, 2012
    The latest developments in drilling rigs can help boost efficiency in quarry producion applications - Mike Woof reports. Efficient drilling and blasting operations can have a huge impact on production costs in quarrying. Accuracy of hole direction and depth, as well as optimum blast design and explosives use, are critical for efficient blasting work. Ineffective blasting can result in high quantities of fines of low commercial value as well as over-sized material requiring secondary breaking. This impacts o
  • Economic and environmental asphalt recycling
    February 27, 2012
    Recycling materials offers the road ahead for highway construction - * Don Brock writes. Recycling has been used in the US for over 50 years in various industries. Today, steel is 100% recycled, and many other products that we have can be recycled.Environmental groups have aggressively pushed industries to recycle more, but it is either economically driven or legislatively driven.In the highway industry it has predominately been economically driven and discouraged by stakeholders such as aggregate producers
  • Concrete surface for runway paving job
    January 18, 2016
    The Fort Lauderdale-Hollywood International Airport in Broward County, Florida, was suffering departure delays on every single flight. The existing 9R-27L runway was too short at 1615m in length, affecting capacity at the airport. To deal with the issue, the Broward County Board of County Commissioners created a plan to extend the southern runway to 2438m to accommodate larger commercial aircraft. The project was not simple however and could not be achieved by tearing out the existing runway and buil
  • Innovative asphalt paver advances for 2015
    April 8, 2015
    Pressure on asphalt paver manufacturers to develop new and more efficient machines is bringing results - Mike Woof writes. For all the key manufacturers in the asphalt paving segment, pressure is being brought to bear with regard to the development of new and more efficient machines. Both for US and European style of pavers, incremental improvements are being seen in machines. In keeping with regulations for Europe and North America, many of the new generation machines are now being powered by the latest lo