The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany.
February 29, 2012 Read time: 3 mins
The BOMAG milling machines worked reliably within a tight time frame
The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany. Upgrade work to the B50 Bundestrasse that connects with the airport is of prime importance and contractor Beitz-Fräsdienstleistungen is widening a 7.5km section of the road. The work will see the road widened and upgraded from two lanes to four-lane and this has been speeded by the high productivity of 172 Bomag planing equipment.

The work was carried out in three different stages with the first stage being planing to a depth of 40mm over a length of 7.5km, an area of 50,000m2. This work removed around 4,500tonnes of material and 180 truck loads were required to haul the milled cuttings away. The second stage was the milling of another 4,500m2 of surface to improve weak points in the road structure, which removed 1,350tonnes of binder and base layers and required a further 55 truck loads to haul the material away. The third and final stage of the milling job was to remove a 150m stretch of 6m wide binder and base layers to a depth of 320mm in front of bridges and this required the removal of 700tonnes of material in a further 28 trucks. In all the milling work required some 6,550tonnes of material to be removed.

The work had to be finished within a tight time frame and the BOMAG BM 2000/60 cold planers worked reliably and productively within the schedule. The planing work had to be completed within a single week during the day from 06.30-17.00 and with a public holiday on the Thursday, the time frame was tighter still. In spite of the surface layer being hard and only a few years old, an average milling speed of 25 m/min was achieved over the 7.5km during the first stage of the planing work. This gave a perfect, clean planed surface that allowed for quick, precise re-laying of the new surface and reduced the time needed for sweeping the road afterwards. During all three stages the average fuel consumption was an encouraging 60-65litres/hour, while cutter wear was minimised due to the effective water spraying system for the planer. Productivity was further boosted by the automatic settings that returned the cutting depth to the same height when each truck carrying the milled material was moved into place under the discharge conveyor.

For more information on companies in this article

Related Content

  • Novel dual layer paving work in Germany
    February 2, 2017
    A German contractor is now using two novel asphalt paving technologies from Vögele together for key projects The firm has acquired Vögele’s InLine Pave equipment with its innovative dual layer paving technology as well as one of the SUPER 1800-3i SprayJets for paving a surface course. This combination of technologies is allowing contractor Rask Brandenburg to carry out fast and efficient road rehabilitation work on some major routes, including a busy Autobahn stretch leading into capital Berlin. T
  • Advanced road recycling with Wirtgen
    November 4, 2019
    Wirtgen has developed its high-performance W 380 CRi cold recycler to meet requirements for roads requiring structural rehabilitation. This innovative machine is said to highly productive, allowing it to carry out structural road rehabilitation more quickly and with greater cost-effectiveness and quality than previous equipment.
  • Kilsaran power paves with Vögele
    July 31, 2012
    Kilsaran, a leading Irish contractor, building materials supplier and producer of concrete products, has completed construction of 11,000m² of hard standing at its first dedicated mortar plant using Vögele's most powerful wheeled paver. The plant in Brownstown, County Kildare, will produce a variety of mortars, including bagged products, for distribution throughout Ireland. The Vögele 1803-2 is one of four such machines operated by the company, and it complements a range of plant, including Hamm compaction
  • Welsh contractor enlists a ‘road warrior’ for stabilisation work in England
    September 28, 2015
    Groundworks contractor DCM Roadways, based in the southeast Wales town of Monmouth, has brought in an FAE MTM to ensure the best result possible for an access road project. DCM, which specialises in soil stabilisation and road recycling, is working on a solar project in the Forest of Dean area of Gloucestershire county, just across the border in England. The job is for the construction of around 1.2km of stabilised highway access roads.