Runway road rehabilitation

The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany.
February 29, 2012 Read time: 3 mins
The BOMAG milling machines worked reliably within a tight time frame
The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany. Upgrade work to the B50 Bundestrasse that connects with the airport is of prime importance and contractor Beitz-Fräsdienstleistungen is widening a 7.5km section of the road. The work will see the road widened and upgraded from two lanes to four-lane and this has been speeded by the high productivity of 172 Bomag planing equipment.

The work was carried out in three different stages with the first stage being planing to a depth of 40mm over a length of 7.5km, an area of 50,000m2. This work removed around 4,500tonnes of material and 180 truck loads were required to haul the milled cuttings away. The second stage was the milling of another 4,500m2 of surface to improve weak points in the road structure, which removed 1,350tonnes of binder and base layers and required a further 55 truck loads to haul the material away. The third and final stage of the milling job was to remove a 150m stretch of 6m wide binder and base layers to a depth of 320mm in front of bridges and this required the removal of 700tonnes of material in a further 28 trucks. In all the milling work required some 6,550tonnes of material to be removed.

The work had to be finished within a tight time frame and the BOMAG BM 2000/60 cold planers worked reliably and productively within the schedule. The planing work had to be completed within a single week during the day from 06.30-17.00 and with a public holiday on the Thursday, the time frame was tighter still. In spite of the surface layer being hard and only a few years old, an average milling speed of 25 m/min was achieved over the 7.5km during the first stage of the planing work. This gave a perfect, clean planed surface that allowed for quick, precise re-laying of the new surface and reduced the time needed for sweeping the road afterwards. During all three stages the average fuel consumption was an encouraging 60-65litres/hour, while cutter wear was minimised due to the effective water spraying system for the planer. Productivity was further boosted by the automatic settings that returned the cutting depth to the same height when each truck carrying the milled material was moved into place under the discharge conveyor.

For more information on companies in this article

Related Content

  • Eurovia races against the clock for London’s Race of Champions
    June 17, 2016
    Fast-track construction has taken on a new meaning following the successful staging of the Race of Champions in London’s Olympic Stadium. The knockout tournament for the world’s best drivers – won by Formula 1 driver Sebastian Vettel – required a super-fast construction and dismantling of a safe, high-speed circuit within the Queen Elizabeth Olympic Stadium. Eurovia UK had just four weeks to design the track, complete trials and mobilise for the project following the contract award. The circuit was co
  • Developments in concrete road construction
    February 7, 2012
    Innovative developments are pushing forward concrete road construction techniques. The concrete road sector looks to benefit from some key innovations and developments now coming to market or being employed in different territories. Irregular weather and environmental conditions can alter the rate at which concrete cures, with a risk of plastic shrinkage cracks that can compromise the integrity of a pavement. Contractors cannot control the environmental conditions of a paving project and when weather patter
  • Road recycling in Denmark
    May 13, 2024
    A novel approach to road refurbishment has saved time, money and carbon emissions in Denmark, while delivering a quality road surface.
  • Road recycling saves time and costs, reduces emissions
    February 13, 2012
    Stabilisers bring recycling improvements to roads in the UK and Armenia. The local road authorities near the UK city of Bath have saved nearly €250,500 on the cost of repairing a 400m long section of the B3110 Midford Road. This saving has been achieved by opting to recycle and strengthen in-situ the existing surface, instead of using conventional full depth pavement reconstruction.